Nagpur’s proposed Rs952.32-crore Kolar-Kanhan barrage near Bina village in Kamptee taluka will require 1,206.96 hectares of land and could submerge 1,198.42 hectares up to the full reservoir level, according to a project document accessed by The Times of India. The proposal has been submitted to Chief Minister Devendra Fadnavis for approval, but land acquisition, rehabilitation and forest clearance processes have not been completed, the document indicates.
The barrage is being planned as a long-term water-security measure for Nagpur. The civic body does not have a reservoir of its own and currently depends on existing water sources and reservoirs to meet the city’s requirements. The proposed project is intended to create an additional buffer for the city’s water needs, subject to administrative approval and subsequent implementation processes.
The land requirement includes 990.646 hectares of government land, of which 17.881 hectares has been identified as defence land. Private land accounts for 198.266 hectares, while 18.048 hectares is classified as forest land and will require examination under applicable regulations.
The project document identifies Juni Kamptee as the gaothan affected by the proposal. The projected submergence area includes the dam seat and is measured up to the full reservoir level. The scale of the land impact means that acquisition, rehabilitation and the treatment of affected landholders will become key administrative issues if the project receives approval and moves towards execution.
The proposed barrage is designed to have a gross storage capacity of 67.88 million cubic metres, including 67.81 million cubic metres of live storage. Its total utilisation for various water requirements has been estimated at 179.601 million cubic metres. The structure will be 438 metres long and have a maximum height of 13.023 metres.
The design includes 16 barrage bays and eight undersluice bays, each 15 metres wide. The structure is planned with vertical-lift gates and a design discharge capacity of 22,443 cubic metres per second. These technical specifications form part of the detailed project proposal currently awaiting a decision on administrative approval.
The project document does not establish that land acquisition, rehabilitation or forest clearances have been secured. The next formal stages will therefore depend on the approval process and the statutory examinations required for government, defence, private and forest land. The proposal’s progress from administrative approval to acquisition and execution will determine how Nagpur’s water-security plans are balanced with the impacts on Juni Kamptee and other affected landholders.