Nagpur’s Besa-Pipla belt is recording about five drinking-water pipeline damage cases every day as road, stormwater drain and sewerage works proceed across the rapidly expanding suburban area, Maharashtra Jeevan Pradhikaran officials told the Times of India. The repeated breaks are disrupting supply for several hours across Besa, Pipla, Beltarodi, Ghogli and Shankarpur.
The damage is being reported as multiple agencies carry out infrastructure works in the same belt. MJP officials said excavation for roads, drains and sewer lines frequently affects existing water pipelines, creating service interruptions for residents and wasting treated water.
The problem has also affected the wider supply network in earlier incidents. A pipeline supplying Besa, Beltarodi, Ghogli and Pipla was damaged during stormwater drain work, leading to the loss of lakhs of litres of water and disrupting supplies to several villages.
Residents said the recurring damage reflected inadequate coordination between agencies working on roads and civic infrastructure. Sonu Karmakar of Ghogli said water supply was the immediate concern for residents whenever a pipeline was damaged. “People’s priority is water. Whenever a pipeline is damaged, the entire area suffers for hours,” he told the Times of India.
Prasanjeet Dutta of Besa said the issue had continued for years because agencies undertaking road and drainage works often did not account for existing pipelines. He had earlier said that an RCC drain being constructed in the middle of a road damaged a drinking-water pipeline.
Residents are also concerned about the location of newer infrastructure. Some water pipelines are reportedly being laid below or alongside stormwater drains, after which cement roads are constructed over them. A future failure could then require the concrete surface to be excavated again, increasing the difficulty of repair and disruption to road users.
The belt has faced wider water-supply stress. Earlier this year, residents of a housing society near Besa-Pipla Road endured a seven-day shortage and relied on private tankers. Previous reporting by the Times of India linked the shortages to development proceeding without adequate planning for essential utilities, leaving authorities to retrofit water and other infrastructure into congested areas.
NP CO Bharat Nandanwar told the Times of India that many MJP pipelines were at least a decade old and had been laid when the roads were much narrower. “Earlier it was a bunch of villages, and only now it is blossoming as a suburban area, so all the roads are being widened. Therefore, it is natural for these pipelines to obstruct the infrastructure development work,” he said.
Nandanwar said MJP could shift pipelines where necessary, citing work completed on the stretch from Besa Square to the Manish Nagar T-point. He also said the agency responsible for damaging a pipeline was responsible for repairing it immediately.
Sources cited in the report said gram panchayats lacked clear records showing pipeline alignments, while roadwork agencies often excavated without consulting MJP. The immediate response therefore remains repair after damage, with pipeline shifting and coordination between agencies identified as the stated next steps where infrastructure works conflict with the existing water network.