The Delhi double-decker flyover between Yamuna Vihar and Bhajanpura has been delayed again, with the remaining construction now expected to be completed by March 2027 after work was disrupted by air-pollution control restrictions. The delay extends the wait for traffic relief in one of northeast Delhi’s major congestion points.
The approximately 1.40-kilometre project is being built at an estimated revised cost of Rs 291.10 crore. Its upper deck carries a metro track, while the lower level is designed as a four-lane road. Metro services on the upper deck began on 8 March 2026, but motorists cannot yet use the road section because construction and the approach ramps on both sides remain incomplete.
The project was announced in 2019 with an initial estimated cost of Rs 220.10 crore. Its completion deadline was first set for 30 December 2024. The target was later extended to July 2025 and then October 2025, with tree-felling and transplantation permissions affecting construction progress. According to the report, work remained stalled for nearly two years before permission for tree felling was received in December 2025.
After that permission, the Delhi Metro Rail Corporation began a fresh tender process for the unfinished ramps and other remaining works. New tenders for the balance construction were issued in April 2026. The completion target was subsequently set for 31 October 2026 and later shifted to December 2026.
The latest delay followed restrictions imposed under the Graded Response Action Plan to control air pollution in Delhi-NCR. External construction activities that generate dust were prohibited until 20 November, affecting the pace of work on the flyover. The project’s revised completion timeline has now moved to March 2027.
The delay means that the metro component is operational while the road component remains unavailable. Vehicles therefore continue to use the existing road network through the Yamuna Vihar-Bhajanpura stretch, where residents have been awaiting relief from congestion. The unfinished ramps remain a key requirement before the lower deck can serve traffic.
Ghonda legislator Ajay Mahawar said efforts were under way to complete the flyover as soon as possible. He said he was maintaining regular contact with the agencies concerned so that the remaining construction could be accelerated. The next stated milestone is completion of the pending work by March 2027.