Hyderabad’s alternative Godavari water supply project has reached its final stage, with officials targeting completion of the remaining pipeline interconnection works within two days and preparing for a trial run, according to the Hyderabad Metropolitan Water Supply and Sewerage Board (HMWSSB).
The 1,600 mm-diameter Mission Bhagiratha–HMWSSB pipeline is intended to carry Godavari water from Mallannasagar to the Ghanpur Master Balancing Reservoir (MBR). The project is designed to provide an alternative to the Singur–Manjeera water sources and reduce the risk of disruptions to Hyderabad’s drinking-water supply.
HMWSSB Managing Director K Ashok Reddy and Mission Bhagiratha Engineer-in-Chief Kripakar Reddy inspected the interconnection works on Friday. They reviewed the progress and technical aspects of the project with officials and directed them to complete the pending works quickly and make arrangements for the trial run.
The pipeline construction and interconnection works had initially been targeted for completion by November 15. According to officials, the schedule was delayed by massive rock layers along a 150-metre stretch of the pipeline passing through a forest area. The remaining work is now being expedited, while the junction works undertaken by HMWSSB at the Ghanpur MBR site have already been completed and are ready for use.
The project is expected to make an additional 40 million gallons per day (MGD) of Godavari water available to Hyderabad. Officials said the transfer of surplus Godavari water could replace about half of the shortfall in supplies to areas dependent on Singur–Manjeera water. The HMWSSB has taken the measure amid declining availability in the Singur–Manjeera sources, which the report attributes to El Niño conditions.
The next reported step is a trial run after the Mission Bhagiratha pipeline interconnection works are completed. HMWSSB and Mission Bhagiratha officials have been asked to coordinate on the remaining technical work and operational preparations.