GMLR Tunnel Project Clears 64 Metres as Second TBM Nears Tests

Mumbai’s Goregaon-Mulund Link Road tunnel project has completed 64 metres of excavation with its first tunnel boring machine, while the second machine is expected to undergo testing in October, the Brihanmumbai Municipal Corporation said on Thursday.

The project’s Phase 3B involves constructing twin underground tunnels between Dadasaheb Phalke Chitranagari, or Film City, in Goregaon East and Amar Nagar in Mulund West. The tunnels will pass beneath the Sanjay Gandhi National Park and are intended to provide a new east-west road connection across the city.

The first tunnel boring machine, named Tulshi, was commissioned on August 17. It has completed 64 metres of excavation and installed 27 ring segments, along with two temporary ring segments, as part of the tunnel construction process.

The second machine, named Vihar, is 92 per cent assembled, according to the BMC. It is scheduled to undergo a Site Acceptance Test from October 13 after installation of its complete system. Subject to the successful completion of the technical tests, excavation of the second tunnel is scheduled to begin on October 22.

The twin tunnels are being constructed from Film City towards Khindipada in Mulund. Each tunnel will be 4.70 kilometres long and designed with three lanes. The tunnels will have a diameter of 14.20 metres, while the section passing through the Sanjay Gandhi National Park will have a diameter of 13 metres.

Tulshi is a single-shield Earth Pressure Balance hard-rock TBM. Its cutter has a diameter of 14.49 metres, while the machine is 83 metres long, including a 22-metre shield section and a 61-metre, three-storey backup gantry. The machine is equipped with an automated muck-handling system comprising a 340-metre conveyor system, a cross conveyor and a stacker conveyor.

The BMC said the muck-handling arrangement is intended to support excavation productivity and safer operations in challenging geological conditions. Underground construction beneath the national park requires the agencies involved to coordinate excavation, machinery, manpower and safety measures throughout the work.

Additional Municipal Commissioner (Projects) Abhijit Bangar inspected the site and reviewed the excavation process, construction activities, technical systems, machinery performance, construction quality and safety measures. He also directed officials to deploy additional manpower and technical staff wherever required to prevent delays.

Bangar instructed officials to prepare a project dashboard containing the percentage of work completed, current project status, excavation progress, daily excavation targets, expected completion details, safety measures and the project schedule. The dashboard, according to the BMC, is intended to provide officials and engineers with a consolidated view of progress.

The municipal official said excavation had begun and that approximately 64 metres had been completed on one side. He directed the agencies to maintain the pace of work in line with the project timeline while ensuring that prescribed safety standards and preventive measures were followed for workers and engineers.

The GMLR tunnel project is targeted for completion by February 2029. The BMC said all agencies involved had been directed to coordinate their work and complete the project within the stipulated timeframe.