Construction on Bengaluru’s suburban railway Corridor 4 has gathered pace, with the 47.774-kilometre route between Heelalige and Rajanukunte being developed through four packages, according to a report by Prajavani quoting officials of B-RIDE/K-RIDE.
The corridor, which will connect southern Bengaluru with eastern and northern parts of the city, comprises 46.560 km of route and 1.214 km of station length. Officials have set a target to complete the project and begin train operations by June 2029.
The first package covers a 9.94-km section between Benniganahalli and Jakkur. The approximately ₹342-crore contract is being executed by a joint venture of RNS Infrastructure Ltd and Gayatri Projects Ltd.
The second package covers the 12.63-km Heelalige–Bellandur section. The ₹511-crore contract, involving construction of at-grade railway track, was finalised in October, the report said.
Tenders for the remaining approximately 19 km, covering the Bellandur–Benniganahalli and Jakkur–Rajanukunte sections, were invited in November. These packages include a double-decker viaduct and have an estimated cost of about ₹445 crore. Bids are scheduled to be opened in January 2027.
The corridor is planned with 19 stations, although Benniganahalli station is being built under Corridor 2. Tenders have been invited for the remaining 18 stations in two packages. Package A includes eight at-grade stations at Heelalige, Singena Agrahara, Huskuru, Ambedkar Nagar, Carmelaram, Bellandur Road, Doddanekkundi and Kaggadasapura, along with an elevated station at Marathahalli. The package is valued at ₹504 crore.
Package B, estimated at ₹528 crore, includes six at-grade stations at Channasandra, Horamavu, Thanisandra, Jakkur, Muddenahalli and Rajanukunte, as well as elevated stations at Hennur, Hegde Nagar and Yelahanka.
The project also includes four road overbridges and one road underbridge to replace five major railway crossings along the corridor, according to officials cited in the report.
Corridor 4 is planned to provide interchange connections with Bengaluru’s metro and suburban railway networks. Benniganahalli is expected to connect with the Purple Line and Corridor 2 of the suburban railway project, while Marathahalli is planned as an interchange with the proposed Blue Line. Yelahanka will connect Corridor 4 with Corridor 1, which runs between KSR Bengaluru and Devanahalli.
The report said work on the suburban railway project had slowed and stopped at various points before being divided into smaller construction packages. It also quoted B-RIDE/K-RIDE managing director Lakshman Singh as saying that trains could run between Chikkabanavara and Yeshwanthpur by the end of 2027 or early 2028 as part of Corridor 2. That timeline is separate from the June 2029 completion target reported for Corridor 4.