An investigation into 24 Pradhan Mantri Gram Sadak Yojana road projects in Bijapur district of Chhattisgarh has identified alleged irregularities worth approximately Rs 19.17 crore, with the state government suspending 13 engineers and beginning proceedings against contractors and five retired officials.
Deputy Chief Minister and Panchayat and Rural Development Minister Vijay Sharma said the investigation found that roadwork recorded in government systems was substantially greater than the work visible on the ground. The projects were intended to connect remote villages in the Maoist-affected district, including Gudma-Aramangi, Pokaram-Dudum, Cherpal-Padmur, Basaguda-Dalla and Lingagiri.
The largest discrepancy involved earthwork. According to Sharma, the government’s online monitoring portal showed approximately 218 km of earthwork as completed, while physical verification found work along only 116 km. The verified work was also described as substandard. The difference of nearly 102 km has raised questions about how construction progress was certified and how payments were authorised.
Sharma said the investigation found excess payments of approximately Rs 19.17 crore for earthwork, murrum laying and other construction activities across the 24 roads. He also alleged that progress reports continued to be uploaded to the central monitoring portal even though several roads remained incomplete, and that incorrect information was entered under pressure from senior officials.
The state government issued show-cause notices to 25 officials and employees. Thirteen were suspended pending departmental inquiries, including three former executive engineers—Suresh Kumar Nagesh, BS Thakur and Jitendra Kumar Meshram—along with six assistant engineers and four sub-engineers. Proceedings have also been initiated against five retired executive engineers. The investigation into the role of other officials associated with the projects is continuing.
Contractors who received payments for the disputed work have also been brought under scrutiny. Show-cause notices seeking recovery have been issued to 15 contractors. Proceedings have begun to recover approximately Rs 5.50 crore from five contractors, while officials have been directed to register first information reports against contractors who do not respond or deposit the amounts sought. The department is recalculating excess payments in other works to establish the total amount recoverable.
The allegations have direct implications for residents of remote settlements that were supposed to gain all-weather road access through the projects. Incomplete or poor-quality roads can restrict access to markets, schools, healthcare and public services, particularly in areas where alternative transport routes are limited.
The government has said fresh tenders have been initiated for 45 roads in Bijapur and 23 in Sukma, with instructions to complete the works by March 2027. It has also set a broader target of completing 148 unfinished roads across Bastar division by March 31, 2027.
Five superintending engineers have been assigned special monitoring responsibilities. Their duties include regular field inspections to verify physical progress, construction quality and compliance with deadlines. The recovery proceedings, departmental inquiries and the completion of replacement works will determine whether the administrative action results in restored connectivity and better oversight of rural road construction.