The Surat-Bilimora section of the Mumbai-Ahmedabad bullet train corridor has been energised for testing, after power supply was started in its overhead electric wires on November 20, Navbharat Times reported. The development clears the way for further testing on the approximately 50-km elevated section in Gujarat.
The section has separate up and down tracks. Power will now be introduced across the section in smaller stretches under the supervision of technical teams and according to prescribed safety procedures, the report said.
The corridor uses a 2 × 25 kV overhead traction system, a configuration used on several high-speed rail networks. The 508-km corridor is planned to have 14 traction substations, which will draw electricity from the national grid and supply it to the overhead equipment.
The first traction substation at Bilimora, in Gujarat’s Navsari district, has had its control panels, changeover switches, transformers and circuit breakers installed, according to the report. The substations in Gujarat will receive power from GETCO’s 220 kV Ambetha grid substation. A central control centre will monitor the wider power network.
With the overhead equipment now live, residents, passengers, workers and other members of the public in the vicinity have been advised to stay away from the wires and associated electrical equipment. The report warned that people should not touch the equipment or undertake any unauthorised work around it because of the high-voltage supply.
The Surat-Bilimora elevated section includes bridges over four rivers and a steel bridge over National Highway 53. About 94,000 noise barriers have been installed along the viaduct to reduce the impact of train noise on nearby communities, the report said.
The energisation is an operational step ahead of testing; the report does not provide a confirmed date for the start of passenger services on this section. It says the first bullet train service is expected next year, but does not specify the exact launch date or the testing schedule.