Bullet Train Corridor: Surat-Bilimora Section Gets Power

The overhead electrical system on the 50-km Surat-Bilimora section of the Mumbai-Ahmedabad Bullet Train corridor in Gujarat was energised on November 20, moving the section closer to electrical and technical testing, the Free Press Journal reported.

Power has been supplied to both the Up and Down lines on the elevated section through a 2 × 25 kV traction system. The energisation will allow engineers to undertake further testing before the section is prepared for high-speed train trials.

The process is being carried out progressively in smaller sections under the supervision of technical teams and safety procedures, according to the report. The corridor’s electrical network is planned to use 14 traction substations, which will draw electricity from the national grid and supply the overhead system.

The first traction substation at Bilimora in Gujarat’s Navsari district has completed installation of key equipment, including control panels, changeover switches, transformers and circuit breakers. The substation is scheduled to receive power from the 220-kV Ambetha Grid Substation operated by Gujarat Energy Transmission Corporation Limited.

The Surat-Bilimora stretch connects the two stations and is entirely elevated. It includes bridges over four rivers and a steel bridge across National Highway 53. The report also said that about 94,000 noise barriers have been installed along the viaduct to reduce the impact of train operations on nearby residential and other areas.

The Mumbai-Ahmedabad corridor is 508 km long. Its electrical system will be monitored through a centralised control centre, with the current energisation marking a step before high-speed train trials on the section. The report did not specify a date for those trials or for passenger services.