West Bengal’s long-term renewable power procurement agreement with an Adani Group company has drawn questions from the Trinamool Congress faction led by Mamata Banerjee, which has sought transparency from the state government over the contract.
The agreement covers an initial 1,750 megawatts of round-the-clock renewable power for 25 years. Adani Energy Solutions Ltd (AESL) said on Saturday that its wholly owned subsidiary, Powerpulse Trading Solutions Ltd, had received a Letter of Award from the West Bengal State Electricity Distribution Company Ltd (WBSEDCL).
The company said the award followed a competitive bidding process. Supply for the initial 1,750MW is scheduled to begin on July 1, 2028.
The Letter of Award also includes a 750MW green-shoe option. If exercised, the additional supply is scheduled to begin on April 1, 2029, taking the total contracted capacity to 2,500MW. A green-shoe option allows a buyer to increase the quantity or capacity covered by an agreement, subject to specified conditions.
The Mamata Banerjee faction of the TMC alleged that the deal raised questions about favouritism and accountability. In a social media post, it said West Bengal’s resources and long-term power contracts required transparency and questioned whether corporate entities had received preferential access.
The party also linked its criticism to broader concerns about access to basic public services, saying that ordinary people continued to face difficulties while some parties appeared to receive out-of-turn benefits.
Neither the BJP nor the West Bengal government had responded to the allegations at the time of the report. AESL’s statement described the procurement as the outcome of competitive bidding but did not address the political accusations.
The agreement is significant for the state’s future electricity planning because it would commit WBSEDCL to a substantial renewable power supply over multiple decades. Its implementation will depend on the contractual conditions of the award, the exercise of the additional capacity option and the scheduled start of deliveries.