Pune Water Supply Disruption Hits Key Areas After Power Faults

Pune water supply disruption affected several central neighbourhoods and suburbs after successive electrical faults at the Parvati water treatment centre and Khadakwasla pumping station reduced pumping capacity over three days. The Pune Municipal Corporation said supply was restored, but several areas continued to receive water late and at low pressure.

The disruption followed a scheduled citywide water shutdown on Thursday. On Friday, a fault in an electrical cable at the Parvati water treatment centre forced the older 350-million-litre-per-day facility to remain closed for four hours. The system was restarted after repairs.

A further breakdown occurred on Saturday when a Maharashtra State Electricity Distribution Company Limited express feeder cable supplying the Khadakwasla pumping station was damaged during construction work. After an alternative power supply was activated, a short circuit occurred when a monkey came into contact with an overhead line, damaging two transformers at the pumping station.

The transformer failure affected pumping operations that supply water to the Warje water treatment centre. The civic body started generators and kept four of the station’s five pumps operating, allowing water to be lifted at about 80% of capacity.

The municipal corporation also hired two transformers, each rated at 1,200 kVA, from a private supplier. One transformer had been installed and commissioned, while the installation of the second was under way. The additional equipment was brought in to support pumping operations while the damaged system was being repaired.

The affected areas include the central peth neighbourhoods, the railway station area, Kharadi, Wadgaon Sheri, Bhandarkar Road, parts of Kothrud, Karvenagar, Shivajinagar and Aundh. Residents in these locations reported delayed water supply and reduced pressure, according to the report.

The civic administration said areas affected by the disruption would be prioritised and pumping would be extended to compensate for the reduced supply. Nandkishor Jagtap, superintendent engineer in the municipal corporation’s water supply department, said engineers had been instructed to monitor the distribution network while efforts continued to stabilise supply.

The sequence of failures affected multiple links in Pune’s water system: scheduled shutdowns, treatment-plant electrical infrastructure, an external feeder cable, transformers and pumping equipment. The municipal corporation’s immediate response focused on temporary power and transformer arrangements, along with additional pumping for neighbourhoods that received inadequate supply. Further restoration work was expected to continue through the evening as the remaining transformer was installed.