HomeAnalysisKaiga Unit 1 Reaches Criticality After 600-Day Overhaul

Kaiga Unit 1 Reaches Criticality After 600-Day Overhaul

Kaiga nuclear power plant Unit 1 in Uttara Kannada district has begun the nuclear fission process after completing a 600-day shutdown for coolant-channel replacement and other maintenance work, according to a report by Prajavani.

The unit achieved criticality at around 1.45am on November 22, the report said. The restart followed approval from the Atomic Energy Regulatory Board and the completion of coolant-channel and feeder replacement activities described in the report as “N-mass” work.

The maintenance outage had kept the unit offline for about 600 days. Officials of the Nuclear Power Corporation of India said the replacement of the coolant channels and other maintenance activities were completed in a short period using indigenous robotic and remote-handling equipment, technical expertise and detailed planning.

Criticality marks the start of the nuclear fission process, but the unit has not yet been connected to the southern grid. According to the officials quoted by Prajavani, mandatory tests must be completed before grid connection. The unit’s electrical output will then be increased gradually to its rated capacity.

The sequence places the immediate focus on testing and staged power escalation rather than on full electricity generation. It also highlights the maintenance requirements of ageing or long-operating nuclear infrastructure, where work on coolant channels and associated systems can require extended outages and specialised equipment.

The officials said the work would strengthen India’s self-reliance in the nuclear power sector. The report did not provide the unit’s rated capacity, the expected date of grid synchronisation or details of the tests still pending. Those milestones will determine when the restored unit begins contributing electricity to the southern grid at its designated operating level.