The Maharashtra Pollution Control Board (MPCB) has ordered an immediate halt to excavation and construction activities at a site linked to the Adani Group’s 1,500 MW Tarali Pumped Storage Project in Satara district, citing alleged work without mandatory permissions.
In a notice issued on November 20, the board directed that ongoing and proposed excavation and development work stop at Gat Nos. 33 and 34 in Savarghar village, Patan taluka. The activities identified in the report include arrangements for a temporary labour camp and storage facilities.
The MPCB action followed an inspection by its Satara officials. According to the notice, the board’s sub-regional officer proposed legal action against the company for carrying out excavation and development activities without the board’s consent. The notice also stated that environmental clearance from the competent authority had not been obtained for activities at the two survey plots.
The board warned that work cannot resume without its prior approval and that non-compliance with the directions could invite legal action.
The reported regulatory concern is linked to the location of the work. The Centre granted environmental clearance to the Tarali project on February 11, 2025, covering 150.74 hectares across Nivade, Tondoshi, Kalambe and Jalu villages in Patan taluka. Savarghar is not listed among the villages specified in that clearance, according to the report.
Rohan Bhatte, honorary wildlife warden of the Maharashtra Forest Department, had complained to the MPCB seeking an independent inquiry into the legality of the work. Bhatte questioned whether the Savarghar site was covered by the project’s existing environmental clearance and whether the company had obtained all required wildlife-related permissions.
He also sought a site inspection and an official panchnama documenting the extent of excavation, construction activity, machinery deployed and the precise locations of the work. The report said he sought legal and criminal action if violations were established.
The MPCB order follows a separate notice issued on November 13 by the Patan Forest Department to the project’s authorised signatory. That notice directed the company to stop work over the alleged commencement of activities without prior approval from the National Board for Wildlife.
The reported orders apply to the activities identified at Savarghar and do not, on the information available, establish that the entire 1,500 MW project has been cancelled or halted. The immediate next step is compliance with the MPCB direction and clarification of the permissions covering the disputed site.