HomeBreaking NewsJuhu Flyover Set for December 2027, BMC Targets 25-Minute Cut

Juhu Flyover Set for December 2027, BMC Targets 25-Minute Cut

Mumbai’s JVPD flyover is now scheduled for commissioning by December 2027, with the Brihanmumbai Municipal Corporation expecting the project to cut peak-hour travel between the western suburbs and Juhu from about 45 minutes to 20 minutes.

The flyover will begin at the end of the CD Barfiwala flyover and extend to the Juhu Versova Link Road. Once completed, it is expected to allow vehicles to bypass at least five congested junctions, including the Juhu Vile Parle Development Scheme circle, which is a major traffic bottleneck in the area.

The BMC had rolled out plans for the project in 2022 to reduce congestion around JVPD. The current completion deadline is December 31, 2027, brought forward from the earlier deadline of March 31, 2028. The proposed structure will be 15.10 metres wide and will include a 72-metre bridge at the 90-feet junction.

The construction involves several engineering challenges because the flyover must pass through a dense and active urban corridor. Girders will be installed beneath the metro station using special technology, while a long span with minimal pillars is planned at Juhu Circle. The design is intended to reduce the number of supports in an area where existing road traffic, junction movements and major utilities compete for limited space.

Utility relocation is also part of the project. The BMC plans to shift 600 mm and 900 mm diameter drains over a distance of 400 metres. A 1,200 mm diameter drain will be relocated using microtunnelling, a method that allows work to be carried out below ground with less surface disruption than conventional excavation.

The project is also planned to connect an arm to the upcoming Versova-Bandra Sea Link, providing direct connectivity towards the coastal road. The supplied report does not specify the construction status of that connection or how the two projects will be synchronised.

Abhijit Bangar, Additional Municipal Commissioner (Projects) at the BMC, said the route currently takes about 45 minutes during peak hours and that travel time is expected to fall to about 20 minutes after completion. He said the flyover would provide relief to traffic in Juhu, Vile Parle West, Andheri West and Versova and make the western suburbs’ transport system more efficient.

The project will therefore depend not only on the construction of the elevated road but also on coordinated work around the metro station, drainage network, junction geometry and planned links to larger coastal transport infrastructure. The next stated milestone is completion and commissioning for vehicular use by December 2027.