GAIL (India) Ltd is seeking a 50:50 joint-venture partner to build and operate a data centre with an initial capacity of at least 5 megawatts (MW) at Chhainsa in Faridabad, Haryana, marking the state-run gas company’s proposed entry into digital infrastructure.
GAIL’s telecom arm, GAILTEL, invited expressions of interest from prospective partners late last month, according to a tender document reported by The Hindu BusinessLine. GAIL would contribute 2,100 square metres of land at Chhainsa and access to part of its optical-fibre cable (OFC) network, while the selected partner would bring data-centre operating experience and participate equally in the proposed joint venture.
The proposed joint-venture company would develop, operate and commercialise data-centre services. The tender document also allows for facilities at other GAIL locations if the Chhainsa project delivers favourable techno-economic results. The sites identified include Gandhar, Vaghodia and Sapar in Gujarat; Babrala in Uttar Pradesh; Bhiwadi and Sohna in Haryana; and Nagpur in Maharashtra.
The plan would extend the use of assets created primarily for GAIL’s gas and LPG pipeline and telecommunications operations. GAIL says it has about 15,800 km of OFC running alongside its cross-country pipelines, connecting more than 100 towns and cities. The land and fibre would be made available to the joint venture on an arm’s-length basis, with their valuation to be determined later, the report said.
For the proposed data centre, however, the joint venture would have to arrange electricity and water. The expression of interest does not specify the source of power or the proposed arrangements for meeting the facility’s electricity requirements. That leaves a central infrastructure question unresolved, since data centres require continuous electricity for servers, cooling systems and supporting equipment.
Connectivity is another key element of the proposal. GAIL’s fibre network could link the facility to telecommunications networks, cloud platforms and enterprise customers, while the availability of land could reduce some early development requirements. The proposed structure would also allow GAIL to access specialised data-centre expertise without developing the operating capability independently.
The partner-selection criteria indicate that GAIL is seeking more than a conventional construction or infrastructure investor. The highest weightage, 30 marks, is assigned to the prospective partner’s offtake commitment—the proportion of the proposed Chhainsa capacity that it agrees to book as a customer. Bidders committing to use at least 80 per cent of the capacity would receive the maximum score in this category.
Financial strength and operating experience make up the remaining criteria. Average annual turnover carries 25 marks, with the highest score reserved for companies reporting at least ₹100 crore over the previous three years. The number of data centres owned by a bidder and the number operated by the bidder or its affiliates each carry 15 marks. A further 15 marks are assigned according to the size of the applicant’s largest data centre, with the top score reserved for facilities with an IT load of at least 25 MW.
These conditions place customer demand and operational capability at the centre of the proposed venture. They could favour established data-centre operators, cloud-service providers, telecommunications companies and technology firms with identifiable computing and storage requirements, according to the report.
GAIL’s proposal comes as demand for data-centre capacity in India grows alongside cloud adoption, digital services, data-localisation requirements and artificial-intelligence-related computing needs. The project would therefore combine a location decision with the reuse of existing public-sector land and fibre infrastructure. At the same time, its viability will depend on issues that remain open in the expression of interest, including partner selection, customer commitments, electricity availability, water arrangements and the eventual valuation of GAIL’s assets.
The tender document also does not establish a construction timetable, a final investment decision or a commissioning date. At this stage, the Chhainsa facility is a proposed joint-venture project rather than an operational data centre. Its progress will indicate whether GAIL can convert pipeline-linked connectivity and land assets into a commercially viable digital-infrastructure platform.