Delhi’s Public Works Department is advancing a four-flyover plan on Mehrauli-Badarpur Road to ease congestion on the stretch between Saket and Badarpur, with two structures under construction and two others still under study.
PWD officials told Live Hindustan that the four projects together are intended to make the roughly eight-kilometre journey between Saket and Badarpur largely free of traffic disruption. The two flyovers already under construction have a target completion date of December 2028.
The Mehrauli-Badarpur, or MB, Road is reported to face lengthy daily traffic jams. According to PWD officials, around four to five lakh people use the road every day. Delhi PWD Minister Pravesh Sahib Singh recently reviewed the status of the two ongoing projects and the proposals for the other two flyovers with officials. He directed officials to complete the construction work on schedule and finish the ongoing studies for the proposed flyovers by January.
The first ongoing project is a 2.41-kilometre flyover between Saket and Sangam Vihar. It will have six lanes, with three lanes in each direction. Around 51% of the work has been completed, and the government’s target is to open it to the public by December 2028. The project is expected to benefit residents of Sangam Vihar and nearby areas by reducing congestion on this section of the road.
A second flyover is being built between Maa Anandmayi Marg and Pul Prahladpur. The structure will be about 2.56 kilometres long and will also have three lanes in each direction. The government approved the project in March, and about 56% of the foundation work has been completed. It too is targeted for completion by December 2028.
The proposed third flyover would connect Sangam Vihar with Maa Anandmayi Marg over a distance of 2.72 kilometres. The project has not yet received government approval. The PWD has appointed a consultant to conduct the study, and a detailed project report is estimated to be ready by January 2027.
The fourth proposal covers the roughly half-kilometre stretch between Pul Prahladpur and Badarpur. Although shorter than the other projects, PWD considers it important for addressing congestion near Badarpur. Government approval is pending, and a study is under way. Its detailed project report is also expected by January 2027.
The two proposed flyovers therefore remain dependent on the outcome of their studies, preparation of the DPRs and government approval. The December 2028 completion target currently applies to the two projects already under construction.