The Finance Ministry has asked ministries to provide detailed explanations before seeking additional budgetary allocations for infrastructure and capital projects whose costs exceed prescribed tolerance levels, according to the Economic Times.
The exercise will cover projects valued at more than ₹5 crore where cost escalation exceeds the 10% threshold. Ministries will have to explain whether the increase resulted from implementation delays, higher input costs, approval-related issues or other bottlenecks. They must also submit revised cost estimates and completion timelines.
Additional budgetary allocations will not be approved without an explanation of the cost change, the reasons for delay and a specific plan for completing the project, the report said, citing people aware of the exercise. The move was discussed during a pre-budget meeting between the Department of Expenditure and ministries and departments.
Large projects undertaken by central public sector enterprises will also be covered where the difference between the originally approved cost and the revised cost is above 15% and exceeds the applicable tolerance level. These projects will similarly require revised estimates, reasons for deviations and updated completion schedules.
The proposed scrutiny places greater responsibility on administrative departments to justify revised budget provisions rather than treating cost escalation as an automatic basis for additional funding. For public infrastructure, that could make the quality of project preparation, approval timelines and implementation monitoring more important in future budget requests.
Projects involving budget-estimate disbursements of ₹150 crore or more are already subject to relevant disclosure requirements, according to the report. The new exercise is intended to strengthen accountability for projects that experience rising costs and prolonged implementation.
The scale of the issue is significant. Data cited by the Economic Times from the Ministry of Statistics and Programme Implementation showed that 1,853 ongoing infrastructure projects valued at more than ₹150 crore, spread across 17 ministries, had incurred aggregate cost overruns of ₹3.22 lakh crore as of October 1.
The Finance Ministry’s approach links any request for additional resources to an explanation of what caused the deviation and how the remaining work will be completed. Its effectiveness will depend on whether revised timelines are monitored after approval and whether departments are held responsible when projects continue to miss their updated schedules.