BMC Pushes Mumbai’s Two 2,000 MLD Bhandup Water Projects

The Brihanmumbai Municipal Corporation has directed officials and contractors to accelerate construction of a 2,000 million litres per day (MLD) water treatment plant and an equally large pumping station at the Bhandup Complex in Mumbai.

Additional Municipal Commissioner (Projects) Abhijit Bangar issued the instructions during an inspection of both project sites on Thursday. He called for closer coordination between departments and agencies, regular reviews and the immediate resolution of construction bottlenecks.

The BMC said the two projects are intended to strengthen Mumbai’s long-term water supply capacity as the city’s population, urbanisation and demand for water increase. The new pumping station is planned to transfer treated water from the treatment plant to the master balancing reservoir.

The existing Bhandup Water Treatment Complex supplies water to large parts of Mumbai. According to the civic body, the complex currently has a combined treatment capacity of 2,810 MLD, comprising two existing units with capacities of 1,910 MLD and 900 MLD.

At the new treatment plant, excavation has reached a depth of 16 metres across approximately six hectares, the BMC said. The project will include a chlorination contact tank, Actiflo technology for removing turbidity and fine suspended particles, flow splitters, dual-media filters, a backwash system, Actidyn treatment and a wastewater pumping system.

Bangar directed officials to complete the remaining excavation by May 31, 2027. He also asked them to plan excavation and debris transportation alongside plain cement concrete work, electrical installations and boundary wall construction. Additional manpower and machinery have been sought to speed up the work. The BMC said excavated debris is being transported to designated locations.

Excavation at the new pumping station has reached 18 metres of the planned 20.5 metres. The excavation required for the bypass pipeline, rising main and pump house building has been completed, while about 85 per cent of the excavation for the inlet chamber and clear water pumping sump is complete.

The BMC said concreting for all 179 micropiles required for the pumping station has also been completed. Bangar instructed officials to prepare detailed schedules, increase manpower and carry out electrical installations alongside civil construction rather than treating the activities as separate stages.

The directions cover civil, electrical, mechanical and water-treatment works. Chief Engineer (Water Supply Projects) Chandrakant Chaudhary and other officials were present during the inspection.

The civic body has said both projects should be completed ahead of their scheduled deadlines. The latest instructions represent an acceleration directive rather than a confirmed revised completion date. Their effect on Mumbai’s water supply will depend on the completion and commissioning of the treatment, pumping and associated transfer infrastructure.