The Deonar dumping ground’s mobile high-mast lighting proposal has come under scrutiny in Mumbai after corporators questioned whether the equipment was available on site and raised concerns over an increase in contractor rates. The BMC Standing Committee nevertheless approved the proposal at its recent meeting.
The lighting arrangement is intended to facilitate night-time dumping at Deonar while biomining and a proposed Waste-to-Energy project remain pending. AIMIM corporator Jameer Qureshi alleged that eight mobile high-mast lights shown in the proposal as deployed since 2026 were not available at the site. He submitted GPS-tagged photographs in support of his claim.
MNS corporator Yashwant Killedar questioned the need for the arrangement while the Waste-to-Energy project was expected to be commissioned the following month, according to the report. He also sought a deadline for completing biomining at the landfill.
A separate procurement concern was raised by NCP corporator Dr Saeeda Khan, who questioned an ₹800 increase in the selected contractor’s rate since 2023. She said rival bidders had quoted increases of only ₹100-200 and called for an inquiry into the difference.
Additional Municipal Commissioner (Projects) Abhijit Bangar said each nine-metre-high mobile mast consumes 12-15 litres of diesel a day. He assured the committee that the required manpower would be provided. Bangar also said the equipment would undergo physical verification and that payments would be withheld until the verification was completed.
The dispute comes as Deonar continues to receive about 600-700 metric tonnes of garbage daily, along with 800-900 metric tonnes of debris used to cover waste, the report said. The BMC has awarded a contract to remediate 185 lakh tonnes of legacy waste and reclaim 110 hectares of land.
The proposed Waste-to-Energy plant is designed to process 600 metric tonnes of waste and generate 7 MW of electricity daily. Its commissioning remains a significant milestone for reducing the pressure on the landfill, but the report did not provide an updated completion date beyond the expectation that it would become operational the following month.
Spread across nearly 120 hectares, Deonar has received waste since 1927. The site continues to contain large quantities of legacy waste despite successive remediation efforts and partial capping. The report linked the landfill’s unresolved conditions to recurring fires, methane emissions and leachate risks affecting surrounding areas.
The BMC’s promised physical verification and decision to withhold payments until that process is complete are now central to resolving the dispute over the mobile lights. The rate allegation, meanwhile, requires the inquiry sought by Khan to establish how the selected contractor’s price was determined and whether the higher rate is supported by the approved scope of work.