HomeBreaking NewsNashik Phata–Khed Highway Moves Towards Construction

Nashik Phata–Khed Highway Moves Towards Construction

The Nashik Phata–Khed elevated highway project in the Pune region has moved closer to construction after land required for the 29.92-kilometre corridor was reportedly secured and the National Highways Authority of India (NHAI) issued a work order to the contractor.

According to Pune Mirror, the NHAI’s Pune project office confirmed that the district administration had handed over documentary possession of the land needed for the project. Construction is expected to begin next month, although the formal appointed date and the contractor’s mobilisation schedule have not yet been stated in the report.

The development follows the completion of the tender process and the issuance of the Letter of Award on October 28. Earlier reports had indicated that the project was awaiting full land possession. At that stage, 163.47 hectares of the 167.27 hectares required for the corridor had been acquired, leaving 3.8 hectares pending.

The state government had assigned the Pimpri-Chinchwad Municipal Corporation, the Maharashtra State Road Development Corporation and the Pune Metropolitan Region Development Authority responsibility for arranging additional land. Up to ₹600 crore had been made available for the acquisition, according to the report.

The project will connect Nashik Phata, Bhosari and Chakan, areas that experience significant commuter and freight movement. The corridor is planned as an eight-lane elevated route, with ground-level road sections and service roads. Its design also includes nine junctions and two major bridges.

The project is expected to reduce the Pune–Nashik journey by about 75 minutes and improve the movement of industrial goods, the report said. These outcomes will depend on the eventual construction schedule and the completed operation of the corridor.

The 29.92-kilometre stretch is being developed in two packages. The first covers 16.73 kilometres and the second 13.18 kilometres. Each package has a proposed construction period of 36 months. The estimated project cost is ₹7,827 crore.

Once completed, the corridor is intended to connect with the wider Pune–Nashik highway route and improve road access between Pune, Nashik and industrial areas along the alignment. For now, the immediate milestones are contractor mobilisation, the formal appointed date and the start of on-ground work.

The reported completion of land acquisition removes a major pre-construction constraint, but the project’s actual delivery timeline will depend on construction progress, site execution and any remaining statutory or coordination requirements.