HomeBreaking NewsHyderabad Godavari Water Link Nears Completion, HMWSSB Says

Hyderabad Godavari Water Link Nears Completion, HMWSSB Says

Hyderabad’s Godavari water link is nearing completion, with the Hyderabad Metropolitan Water Supply and Sewerage Board (HMWSSB) targeting the end of connection work by November 21, according to a statement cited by Siasat.

The project involves connecting a 1,600-millimetre Mission Bhagiratha-Jalmandali pipeline from Mallannasagar to the Ghanpur Master Balancing Reservoir (MBR). The link is intended to provide Hyderabad with an additional drinking-water source and reduce dependence on the Singur-Manjeera system.

HMWSSB Managing Director Ashok Reddy and Mission Bhagiratha Engineer-in-Chief Kripakar Reddy inspected the connection work on November 20. The original target was November 15, but work was delayed by the removal of heavy rock layers along a 150-metre section passing through forest land, the Water Board said.

The junction work inside the Ghanpur MBR premises has been completed and is ready for use, according to the statement. HMWSSB said it would arrange a trial run after the Mission Bhagiratha pipeline connection is finished.

The Water Board has set a target of drawing 40 million gallons per day (MGD) from the Godavari system. It said the additional water would help cover the deficit in areas dependent on Singur-Manjeera reservoirs, where availability has been declining. HMWSSB attributed the reduction to El Niño conditions.

The project is being advanced as an alternative supply arrangement for the city. However, the report does not provide a date for regular distribution to households or details on the water quality and operational results of the planned trial run. Those outcomes will determine when the additional source translates into a reliable increase in municipal supply.