HomeBreaking NewsSammakka Sagar Barrage Gets NOC Push as Chhattisgarh Vows Faster Process

Sammakka Sagar Barrage Gets NOC Push as Chhattisgarh Vows Faster Process

Telangana Chief Minister A. Revanth Reddy has sought Chhattisgarh’s No Objection Certificate (NOC) to store water in the completed Sammakka Sagar Barrage, with Chhattisgarh Chief Minister Vishnu Deo Sai assuring him that the approval process would be expedited.

Revanth Reddy and Telangana Irrigation Minister N. Uttam Kumar Reddy met Sai on Tuesday and requested cooperation in securing the NOC and other pending clearances for the project. The Telangana government said the permission is needed to store Godavari water in the barrage, which is intended to support irrigation and drinking water requirements in drought-prone, backward and tribal regions.

During the meeting, Revanth Reddy said Telangana’s water requirements could increase because of El Niño conditions. He urged Chhattisgarh to process the approval in the public interest and said Telangana was prepared to bear expenses related to land acquisition, compensation and rehabilitation in Chhattisgarh according to applicable norms.

The Sammakka Sagar Barrage has been constructed at Tupakulagudem in Mulugu district and is complete. At its Full Reservoir Level of plus 83 metres, the barrage has a storage capacity of 6.94 TMC. Its operation, however, requires the remaining inter-state permissions because part of the reservoir area extends into Chhattisgarh.

The project was initially proposed at Kantalapalli, where the expected submergence was estimated at around 11,408 acres. The site would have affected 17 tribal villages and security infrastructure. To reduce the impact, the barrage location was shifted to Tupakulagudem.

An IIT Kharagpur study commissioned at the request of the Chhattisgarh government estimated that around 33 acres in Chhattisgarh would be submerged at the barrage’s Full Reservoir Level. The affected area is expected to remain below 100 acres even during severe floods, according to the study’s findings cited in the report.

Telangana paid Rs.9.883 crore in April towards the study requested by Chhattisgarh. IIT Kharagpur submitted its report to the Chhattisgarh government on July 30, providing the technical assessment being used in discussions over the NOC.

The pending approval is significant because the barrage’s intended benefits depend on its ability to store and regulate Godavari water. Telangana has positioned the project as a source of water for irrigation and drinking needs in regions identified as drought-prone and tribal, while the land and rehabilitation commitments relate to the limited area expected to be affected in Chhattisgarh.

Sai’s assurance that the NOC process would be expedited is the latest development in the inter-state clearance process. Telangana is now seeking the formal NOC and other remaining permissions required for the project’s operation.