Telangana Chief Minister A. Revanth Reddy has asked Chhattisgarh Chief Minister Vishnu Deo Sai to expedite a No Objection Certificate for storing Godavari water in the completed Sammakka Sagar Barrage, with Sai assuring that the process would be fast-tracked.
Revanth Reddy and Telangana Irrigation Minister N. Uttam Kumar Reddy met Sai on Tuesday and sought his cooperation in securing the NOC and other pending clearances for the project. The Telangana government said the approval was important to enable water storage at the barrage and support irrigation and drinking-water requirements in drought-prone, backward and tribal regions.
During the meeting, Reddy said Telangana’s water requirements could rise because of El Niño conditions. He stressed the need to store Godavari water in the barrage and requested that the neighbouring state complete the approval process in the public interest.
The Sammakka Sagar project was originally proposed at Kantalapalli. That location was expected to submerge about 11,408 acres, affect 17 tribal villages and impact security infrastructure. To reduce the extent of submergence, the barrage site was shifted to Tupakulagudem in Mulugu district.
An IIT Kharagpur study commissioned at the request of the Chhattisgarh government estimated that about 33 acres in Chhattisgarh would be submerged at the barrage’s Full Reservoir Level. Even in severe flood conditions, the affected area is expected to remain below 100 acres, according to the project details cited in the report.
Telangana paid Rs.9.883 crore in April towards the study requested by Chhattisgarh. IIT Kharagpur submitted its report to the Chhattisgarh government on July 30, providing the assessment required for consideration of the NOC.
The barrage has been constructed at Tupakulagudem and is complete. At a Full Reservoir Level of +83 metres, it has a storage capacity of 6.94 TMC. The project is intended to use Godavari water for irrigation and drinking-water needs in areas identified as drought-prone, backward and tribal.
Reddy also assured Chhattisgarh that Telangana was prepared to bear expenses related to land acquisition, compensation and rehabilitation in the neighbouring state in accordance with applicable norms. The assurance addresses the costs associated with the limited submergence identified in the IIT Kharagpur assessment.
The remaining step highlighted in the meeting is Chhattisgarh’s NOC, along with other pending clearances. Sai’s assurance that the process would be expedited is the latest stated development in Telangana’s effort to operationalise water storage at the Sammakka Sagar Barrage.