Waaree Energy Storage Solutions has started commercial production at a 5.15 GWh annual-capacity battery pack manufacturing line in Rola, Gujarat, adding a new domestic manufacturing capability for energy-storage systems used by utilities, commercial and industrial customers and infrastructure projects.

The facility is located in Gujarat’s Valsad district and marks the second milestone in Waaree ESS’s planned 20 GWh energy-storage manufacturing expansion, according to an official company release reported by The Hindu BusinessLine. The company is a subsidiary of Mumbai-based Waaree Energies Ltd.

The battery pack line follows the commissioning of a 5.15 GWh Battery Energy Storage System container manufacturing facility at the same location in July 2026. With both facilities now operational, Waaree ESS said it is moving towards an integrated domestic energy-storage manufacturing value chain.

The company’s expansion is backed by ₹1,003 crore raised from strategic investors in January 2026. The fundraise forms part of the Waaree Group’s wider ₹10,000 crore capital-expenditure plan to establish 20 GWh of advanced lithium-ion cell and battery-pack manufacturing capacity.

Battery packs and BESS containers are components of larger energy-storage systems that can support electricity infrastructure and industrial users. Waaree ESS said its products and integrated solutions are intended for utilities, commercial and industrial customers and infrastructure projects. The company’s manufacturing roadmap covers lithium-ion cells, battery packs and utility-scale battery energy-storage systems.

The latest commissioning places battery-pack production ahead of the company’s planned lithium-ion cell manufacturing milestone. Waaree ESS said cell manufacturing is the next step in its roadmap, but the release did not provide a commissioning date or additional capacity details for that facility.

“Commencing commercial production on our 5.15 GWh battery pack manufacturing line marks a major milestone in building Waaree ESS’s fully integrated, Made-in-India energy storage value chain,” Sunil Rathi, Director-Sales, Waaree Energies, said in the company statement.

“With battery packs and BESS containers now manufactured at Rola, and lithium cell manufacturing next on our roadmap, we are strengthening domestic capabilities to meet India’s growing demand for utility-scale and commercial and industrial energy storage,” Rathi said.

The company’s announcement comes as its planned manufacturing chain expands from BESS containers and battery packs towards lithium-ion cells. The operational facilities at Rola are expected to serve as the current manufacturing base for the two completed stages of the roadmap, while the next milestone remains cell production.