Maharashtra’s forest department has reviewed the proposed 1,500 MW Tarali pumped storage hydroelectric project in Satara district after a dispute over its declared project cost, wildlife conservation payments and approvals for work near the Sahyadri Tiger Reserve and Koyna Wildlife Sanctuary.
State forest minister Ganesh Naik chaired the review meeting on Tuesday, which was attended by officials from Adani Green Energy Ltd (AGEL), the company developing the project. According to official sources cited by Times of India, the government may consider withdrawing the forest department’s demand that AGEL contribute 4% of the total project cost towards wildlife conservation around the protected areas.
The demand was issued through a letter from the Principal Chief Conservator of Forests (Wildlife). AGEL has said the project’s total estimated capital cost is Rs 5,675 crore. The company clarified that an earlier figure of Rs 56.75 crore referred only to preliminary activities, including surveys, investigations, geological exploration, engineering studies, detailed design, field investigations, testing and other work required for feasibility assessment.
AGEL said it had sought wildlife clearance for those preliminary activities and that the State Board for Wildlife cleared the proposal in March. The company also stated that it deposited 1% of the applicable cost related to the survey and investigation proposal with the government.
The meeting reviewed the project’s requirements, proposed environmental conservation measures and recommendations from the forest department. Officials also discussed the eco-sensitive zone around the wildlife sanctuary. In the absence of a specific eco-sensitive zone notification, a 10-km radius applies to the project under Supreme Court guidelines, according to the report.
AGEL said in a written clarification to the chief wildlife warden and the Principal Chief Conservator of Forests (Wildlife) that the Union Ministry of Environment, Forest and Climate Change granted environmental clearance in February last year. The Maharashtra Pollution Control Board granted consent to establish in April, the company said.
The company further stated that no forest land is involved in the project and that it had obtained a non-forest land no-objection certificate. After completing formalities and receiving permission from the State Board for Wildlife for site investigations, AGEL said it submitted a fresh proposal on November 5 seeking National Board for Wildlife approval for the full project. That proposal listed the project cost as Rs 5,675 crore, matching the figure in the environmental clearance.
The state forest department issued a stop-work notice on November 13, directing that work at the site be halted. The notice cited the commencement of work without approval from the National Board for Wildlife.
The dispute followed representations by Satara’s Honorary Wildlife Warden, Rohan Bhate, who last month raised concerns about an alleged discrepancy in the project cost submitted to the state government. Bhate said the cost had earlier been shown as Rs 56.75 crore instead of Rs 5,675 crore and sought an independent inquiry from the National Board for Wildlife, the environment ministry and the chief minister.
Bhate argued that understating the cost could amount to misrepresentation and affect wildlife conservation contributions linked to the project’s value. The government’s review will determine how the forest department’s demand, the stop-work direction and the pending wildlife approval are handled. AGEL’s proposal for National Board for Wildlife approval remains a key next step before the full project can proceed.