HomeAnalysisSJVN Awards 2,000 MW Pumped Storage Capacity Across India

SJVN Awards 2,000 MW Pumped Storage Capacity Across India

SJVN Limited has announced the winners of its December 2025 auction for developing 2,000 MW of pumped storage projects (PSPs) across India, assigning capacity to six companies under annual tariffs ranging from Rs 14.1 million to Rs 14.5 million per MW.

Avaada Water Battery secured 260 MW and ReNew Hydro Storage won 500 MW at an annual tariff of Rs 14.1 million per MW. Wiso Energy Four was awarded 330 MW at Rs 14.3 million per MW annually.

Chinta Green Energy secured 300 MW, while Tata Power Company and Greenko Energies won 330 MW and 280 MW, respectively. These three awards carry an annual tariff of Rs 14.5 million per MW. The six allocations together total 2,000 MW.

According to Renewable Watch’s report, the projects are required to provide eight hours of discharge, with a maximum of five hours of continuous discharge. They must also maintain at least 95 per cent annual availability and achieve a minimum round-trip efficiency of 75 per cent. The specified maximum conversion loss is 25 per cent.

The selected developers will be responsible for acquiring land, arranging grid connectivity up to the interconnection point and delivering the projects through end-to-end engineering, procurement and construction. Their obligations will also include operations and maintenance.

All awarded capacities are required to be commissioned within five years. The auction conditions provide for liquidated damages in case of delays, while delays extending beyond six months may lead to capacity termination, the report said.

Pumped storage projects use electricity to move water to an elevated reservoir and generate power when required. Their inclusion in the auction places emphasis not only on installed capacity, but also on discharge duration, availability and round-trip efficiency. These conditions will determine how effectively the projects can support the electricity system once operational.

The allocation also places significant execution responsibility on developers. Land acquisition, grid connection and construction are not being treated as separate public-sector delivery obligations in the reported terms; they form part of the selected companies’ responsibilities. This makes the five-year commissioning requirement a key implementation milestone for the awarded capacity.

Separately, SJVN signed a 110 MW wind power purchase agreement in November 2026 with Adyant Alpha Power Private Limited, a Datta Infra Group company, for a wind power project in Davanagere, Karnataka, according to the report.