Sandur Manganese & Iron Ores Ltd plans to invest about Rs 280 crore in its first in-mine iron ore beneficiation plant in Karnataka to upgrade lower-grade ore for pellet manufacturing, the company said in a regulatory filing reported by PTI.
The first unit, with a designed capacity of 3.5 million tonnes per annum, is expected to initially produce 1-1.2 million tonnes of upgraded ore. The company said output could eventually rise to 1.7 million tonnes.
The plant will process ore from the company’s KTIO mines and some ore from its Deogiri mines. It is designed to upgrade ore containing about 50 per cent iron into a concentrate with more than 60 per cent iron content for pellet production.
The project is being implemented in two phases. Sandur Manganese has a long-term plan for two 3.5 MTPA units, although the current announcement concerns the first facility. The company said the first unit was about 25 per cent complete, with civil works progressing, structural fabrication underway and orders placed for long-lead items.
Commissioning is targeted for August next, according to the company. The project is expected to be financed through a combination of debt and internal accruals.
Managing Director Bahirji A Ghorpade said the plant would improve the quality and marketability of lower-grade ore, reduce waste and support better revenue realisation.
The proposed beneficiation facility represents an investment in processing capacity closer to the company’s mining operations. Its stated purpose is to increase the usable value of lower-grade iron ore before pellet manufacturing, rather than relying solely on direct use of higher-grade material. The company has operations spanning manganese and iron ore mining, ferroalloys, coke and energy, and speciality and alloy steel through Royal Sandur Metals.