Fabrication of four specialised orthotropic steel deck structures for Mumbai’s Versova-Bandra Sea Link has begun in China, according to project officials, marking progress on one of the most technically demanding components of the open-sea road project.
The Maharashtra State Road Development Corporation (MSRDC) has engaged specialised Chinese agencies for the fabrication work. The orthotropic steel deck structures are expected to be launched before the 2027 monsoon, when marine construction activity is scheduled to stop because of unfavourable sea conditions.
The Versova-Bandra Sea Link involves construction in rough and choppy open-sea conditions, making marine operations more difficult than work carried out in relatively sheltered waters. Officials said construction teams have limited working windows during the year, while operations come to a complete halt during the monsoon.
The project is targeted for completion by May 2028. However, officials indicated that the difficult marine conditions and specialised engineering requirements could result in an extension of a few months.
The four orthotropic steel decks will have 120-metre navigational spans and will incorporate box-girder and bow-string arch designs. Orthotropic steel deck technology is lighter than conventional concrete or composite bridge systems while providing high structural strength, according to the report.
The main bridge is planned to include a 300-metre cable-stayed section with a 150-metre navigational span, as well as balanced cantilever bridges measuring 223 metres. The wider project also includes connectors at Juhu, Carter Road and Versova.
Fabrication of the steel superstructures for the Carter Road and Versova connectors is being undertaken in India through specialised agencies. The Juhu connector is planned as a 240-metre cable-stayed bridge with a central pylon. The Versova connector will include a cable-stayed bridge with a 120-metre clear span designed to reduce mangrove felling, according to project officials.
The fabrication and launching schedule will be important to the project’s construction calendar because marine works cannot continue through the monsoon. The project’s completion date therefore remains linked to the availability of safe working windows, the progress of specialised fabrication and the installation of the structures at sea.