The Maharashtra Pollution Control Board (MPCB) has ordered Adani Renewable Energy One Ltd to stop excavation and construction for a temporary labour camp and storage facilities in Satara’s Patan taluka, alleging that the work began without required permissions and environmental clearance.
The direction, dated November 20, applies to Gat Nos. 33 and 34 in Sawarghar village, where land was being developed for temporary construction-support facilities linked to the company’s 1,500 MW Tarali Pumped Storage Project. The MPCB said work must stop forthwith and must not resume without its prior permission.
The order was issued under Section 33A of the Water (Prevention and Control of Pollution) Act, 1974, and Section 31A of the Air (Prevention and Control of Pollution) Act, 1981. According to the report, MPCB officials inspected the site on November 20, after which the Satara Sub-Regional Officer submitted a proposal for legal action.
The Board identified the alleged commencement of excavation and development without the necessary consent and permissions, and the absence of environmental clearance for the activities, as major instances of non-compliance. It also stated that the work had allegedly been undertaken without adequate pollution-control measures, causing air and water pollution.
The company disputed the scope of the action. An Adani Renewable Energy One spokesperson said the MPCB communication related specifically to the two plots earmarked for temporary construction-support facilities, which were not permanent project components. The spokesperson said the permanent components had the requisite statutory clearances and that the temporary use of the private land had been considered in the approved layout of the Central Electricity Authority.
The company said the temporary facilities would be dismantled after construction and the land restored, as applicable. It added that activities at the two plots had been kept in abeyance while it submitted facts and clarifications to the MPCB, and said it remained committed to applicable statutory and environmental requirements.
The project has also faced controversy over reports that its declared project cost was reduced by 99 per cent, lowering a mandatory contribution to the Sahyadri Tiger Reserve from Rs 227 crore to approximately Rs 2.27 crore. The company has denied those allegations.