The Maharashtra Pollution Control Board (MPCB) has directed Adani Renewable Energy One Ltd to stop excavation and construction for a temporary labour camp and storage facilities in Satara district, stating that the work began without the required environmental clearance and permissions.

The site is in Sawargahar village in Patan taluka and forms part of the company’s 1,500 MW Tarali Pumped Storage Project. The MPCB issued its stop-work notice on November 20 after officials inspected Gat Nos. 33 and 34, according to the notice reported by Press Trust of India.

The board said the company had started excavation and development work for the temporary camp and related storage activities without informing it or securing permission from the competent authority. The direction covers all ongoing and proposed excavation and construction activity at the site.

Issued under Section 33A of the Water (Prevention and Control of Pollution) Act, 1974, and Section 31A of the Air (Prevention and Control of Pollution) Act, 1981, the notice bars the company from resuming work without prior permission from the MPCB. It also warns that non-compliance could lead to legal action under the relevant environmental laws.

The MPCB said its site visit was followed by a proposal from the Satara sub-regional officer for legal action. The board had granted the company consent to establish the standalone pumped storage project in April 2025, subject to specified terms and conditions, the notice said.

The stop-work direction places the temporary construction facilities under regulatory scrutiny while the wider pumped storage project remains subject to the permissions and conditions imposed by the pollution control authority. The report did not provide a response from Adani Renewable Energy One Ltd or details on the company’s next steps.