The Ministry of Road Transport and Highways (MoRTH) has proposed a comprehensive revision of the model Request for Proposal (RFP) for highway Engineering, Procurement and Construction (EPC) contracts, linking contractor eligibility more closely to project performance and execution delays.
The proposed framework, reported by PTI on Thursday, would update the model RFP issued in March 2019. MoRTH said the changes are intended to encourage performance-oriented contractors, improve quality and accountability, and make highway bidding and contract awards more transparent.
The revision covers six RFP sections, 12 appendices and nine annexures to Appendix-IA, along with three new formats, according to the ministry. Under the proposed approach, a contractor’s bid capacity would depend on its performance rating and delays in ongoing projects, replacing the earlier method based on the contractor’s best-performing financial year.
Existing project commitments would also be weighted according to execution delays. Bidders would have to disclose ongoing disputes, litigation, arbitration and penal actions, and keep those details updated during the bidding process.
MoRTH has proposed removing sequential counter-offers to the second- and third-lowest bidders. If the lowest bidder is found ineligible, the authority may annul the process and invite fresh bids, the ministry said.
The proposed changes would reduce the maximum number of joint-venture members from three to two. Joint ventures would generally be permitted for projects valued above Rs 1,000 crore, with enhanced minimum participation requirements for the other member.
Performance security would be linked to contractor ratings and range from 3 per cent to 5 per cent of the bid price. The framework would also permit electronic submission of security instruments.
MoRTH said identified non-performance criteria would be rationalised from 20 to seven, with defined thresholds and look-back periods. Provisions concerning catastrophic failures, project termination, debarment and insolvency would also be strengthened.