Makarba–Corporate Road signal work set to resume in 3–4 days

Ahmedabad Municipal Corporation (AMC) has said traffic signals at the junction where the Makarba–Corporate Road overbridge ends will be made operational within three to four days, after the required NOC related to overhead-line height and distance was submitted to Torrent.

The clarification follows continuing congestion near the overbridge and delays in completing signal installation at the junction. According to a Gujarat Samachar report published on November 19, signal poles have already been erected, but the work was held up during the process of obtaining the NOC bond.

The AMC rejected the explanation that high-tension lines themselves had prevented the signals from being installed. It said the delay was linked to the formal approval process concerning the clearance between the proposed signal infrastructure and the overhead line.

The junction had earlier seen the use of a “capsule system” as traffic authorities responded to congestion after the overbridge was opened. The report said traffic disruption has continued, while signal installation remained incomplete.

The civic body said the NOC had been submitted to Torrent on the previous day and that the remaining work would be completed within three to four days. It also said police had provided one written opinion on the matter, while additional representations had been made verbally to AMC engineers during their visits along the route.

The signal installation is intended to regulate vehicle movements at the point where the Makarba overbridge joins Corporate Road. Until the signals become operational, commuters using the junction continue to face the traffic conditions described in the report. The three-to-four-day timeline is an AMC commitment and will depend on completion of the remaining installation and commissioning work.