The Kolkata Metro Orange Line’s 4.5-km extension between Beleghata and Salt Lake Sector V has moved closer to passenger operations after trial runs began, but the stretch cannot open until it receives clearance from the Commissioner of Railway Safety (CRS).
The extension will add three stations—Gour Kishore Ghosh, IT Centre and Nalban—and create a direct Metro connection between Kavi Subhash, also known as New Garia, and Sector V. The journey is expected to take about 30 minutes once services begin.
According to the report, Rail Vikas Nigam Limited (RVNL) is executing the extension. A trial run was conducted on October 10, 2026. A senior Metro Railway official said the line could be inaugurated by the end of 2026, subject to CRS approval. No inauguration date has been confirmed.
The project had faced delays around the Chingrighata area, where a 366-metre viaduct section remained incomplete. The report said a 62-metre section between pillars 317 and 319 was installed in two phases, involving 28-metre and 34-metre spans. Each phase required a 60-hour construction window. Work had previously remained halted for nearly one-and-a-half years because of delays in obtaining the required clearances.
For passengers, the extension would remove the need for a road journey or an interchange for direct travel between south Kolkata and Sector V. Residents of Garia, Mukundapur, Patuli, Anandapur and Kalikapur, along with employees travelling to the information-technology district, are among the likely users. Suburban railway passengers arriving at New Garia from Diamond Harbour, Sonarpur, Canning and Baruipur could also access the Orange Line through Kavi Subhash station.
The IT Centre station is expected to connect with the Green Line’s Salt Lake Sector V station through a footbridge. This would allow passengers to continue towards Sealdah, Howrah and Esplanade with an interchange. The extension may also improve public-transport access to hospitals along the Eastern Metropolitan Bypass, including Medica, Ruby, Peerless and RN Tagore.
The project’s next decisive step is the CRS inspection and approval process. Passenger services cannot begin solely on the basis of trial runs, and the final start date will depend on regulatory clearance and an official announcement by Metro authorities.
The proposed link is also being watched in property markets along the corridor. The report cited indicative average asking rates of about ₹10,200 per sq ft in Salt Lake Sector V, ₹8,450 in Beleghata, ₹11,700 in Anandapur, ₹11,150 in Mukundapur, ₹5,487 in Kalikapur, ₹5,450 in Garia and ₹5,212 in New Garia. These figures describe existing market asking trends and do not establish that the extension has caused any price change.