Kamathipura Cluster Redevelopment Set for February 2027

The Kamathipura cluster redevelopment in south Mumbai is expected to move into physical construction in February 2027, after the Mumbai Repairs and Reconstruction Board secures consent from at least 51% of residents, according to Sanjeev Jaiswal, vice-president of the Maharashtra Housing and Area Development Authority (MHADA).

The authority has opened a consent-registration centre, a project office and a sample flat in a building in Kamathipura. The facilities were inaugurated on Friday in the presence of MPs Milind Deora and Arvind Sawant, MLA Amin Patel and Jaiswal. The facilities are intended to support the next stage of the project: determining residents’ eligibility and collecting their consent.

Jaiswal said the consent process would be accelerated and that the required 51% approval should be obtained by 7 December. Further action would then be taken to begin the redevelopment work in February 2027. The report does not provide a detailed schedule for individual buildings, resident relocation or construction phases.

The planned redevelopment covers 34 acres and involves 943 buildings, with approximately 8,000 residents to be rehabilitated, according to the report. The project is being undertaken on the lines of the redevelopment model used at Motilal Nagar, although the report does not set out the specific terms of that comparison.

A tender has awarded the project’s construction and development agency role to Bhagirathi Housing Pvt Ltd and Mathi Developers, identified in the report as AATK Construction. The contract between the Mumbai Repairs and Reconstruction Board and the contractor was signed after a detailed project plan was presented to residents.

The opening of the consent centre marks an administrative step rather than the start of construction. Before work can begin, the authorities and contractor must establish residents’ eligibility and complete the stated consent process. The sample flat is intended to give residents a physical reference for the proposed rehabilitation housing, but the report does not specify its area, amenities, allotment rules or the number of replacement homes.

For residents, the immediate significance is the shift from project planning to consent collection. The scale of the site means that eligibility decisions, documentation and the handling of residents during construction will be central to the project’s implementation. The available report confirms the authority’s target dates and the project’s broad scope, but further details on phasing, temporary accommodation, rehabilitation guarantees and grievance mechanisms have not been disclosed.