Jakkur railway overbridge opens after 15-year delay

Bengaluru’s Jakkur railway overbridge has opened after a 15-year project history marked by land-acquisition disputes, a change in the implementing agency and prolonged delays in issuing a fresh work order. The 443-metre bridge is expected to ease movement for commuters in north Bengaluru.

The Rs 69.6-crore project was initiated by South Western Railway (SWR) in 2011. Construction stalled in 2014 over land-acquisition problems, after which the project was handed over to the Bruhat Bengaluru Mahanagara Palike (BBMP) in 2018 on an “as-is-where-is” basis, according to Bengaluru development minister Krishna Byre Gowda.

The land requirement covered 6,733 square metres across 48 properties. Most owners rejected compensation options such as transferable development rights and sought cash compensation instead. This significantly increased the land-acquisition component of the project: Rs 43.5 crore, or more than half of the total expenditure, was attributed to land acquisition.

In 2017, BBMP adopted a direct-purchase approach under the Karnataka Municipal Corporations Act and acquired 33 properties for Rs 25 crore. However, the project continued to face difficulties involving two properties in the Bangalore Development Authority’s Arkavathy Layout.

Those properties were under the oversight of the Justice Keshavanarayana Committee. While BBMP acquired other parcels through compulsory acquisition, deposited compensation with the court and proceeded with construction, the two properties remained unresolved. The committee cleared the land required for the bridge’s down ramp only in August 2025.

A separate delay followed the transfer from SWR to BBMP. After SWR’s exit in 2018, the civic body took nearly six years to issue a fresh work order, which was done in 2024. Pending land acquisition was cited as the reason for the delay.

Gowda said he began following up on the project after Deputy Chief Minister DK Shivakumar directed officials to expedite the work. The minister also said Shivakumar allocated funds to complete the bridge and provide cash compensation for land acquisition. Gowda attributed the lack of progress between 2018 and 2023 to the previous BJP government.

The Jakkur project shows how a relatively defined transport link can remain incomplete when construction responsibility changes before land and compensation issues are settled. In this case, the bridge itself accounted for a smaller share of the reported cost than acquiring the land needed to build it. The sequence also left BBMP managing legacy constraints created during SWR’s implementation and dealing with land governed by a separate development authority and committee process.

For residents and commuters, the opening provides the immediate benefit of a new grade-separated crossing. For Bengaluru’s infrastructure agencies, the project leaves a more durable administrative lesson: land availability, compensation decisions and inter-agency approvals need to be resolved early enough to prevent a project from being transferred before its core implementation risks are addressed.