Jaipur Development Authority officials will verify the boundary of railway land before proceeding with widening work on the 22 Godam–B-2 Bypass corridor, following directions from Rajasthan Urban Development and Housing Minister Jhabar Singh Kharra, Dainik Bhaskar reported on November 26.
The officials have been instructed to examine old railway settlement records from 1925 and 1952–55 and compare them with measurements and conditions on the ground. If the railway is found to occupy land beyond the area recorded as allotted or acquired, the JDA may classify the excess area as encroachment and issue notices under its rules, according to the report.
The railway administration will be able to submit land-related records and other evidence. The JDA will assess the legal validity of those documents before deciding further action. The reported directions also call for any discrepancies between historical records and current measurements to be examined on the basis of available facts.
The widening plan covers about 7.5 km in three sections. The 2.7-km stretch from 22 Godam to Mahesh Nagar railway crossing is proposed to be 40 feet wide. The 1.9-km section from Mahesh Nagar railway crossing to the Gopalpura Bypass underpass is proposed at 60 feet, while the 2.9-km stretch from the Gopalpura Bypass underpass to B-2 Bypass is proposed at 80 feet.
The report said around 64 constructions have been identified within the road boundary during inspections between the Public Works Department underpass and the B-2 Bypass area. Red markings have reportedly been placed on portions extending between eight and 14 feet into the identified road boundary.
The master plan had earlier proposed a 100-foot-wide road across the entire route, while the subsequent zonal plan specified different widths for the three sections. Once developed, the corridor is expected to provide a direct alternative connection between B-2 Bypass and 22 Godam and help reduce traffic pressure on Tonk Road, the report said.