HomeAnalysisJaipur North Ring Road Faces Fresh Delay Over Land Acquisition

Jaipur North Ring Road Faces Fresh Delay Over Land Acquisition

Jaipur’s proposed North Ring Road is facing another delay after the National Highways Authority of India (NHAI) failed to advance the next stage of land acquisition, according to a report by Dainik Bhaskar. The project has now reached a time-sensitive point: unless the final land acquisition notification under Section 3D of the National Highways Act, 1956, is published by 4 December, the earlier Section 3A notification could lose effect and the process may have to be restarted.

The Jaipur district administration has completed land measurement, alignment marking and boundary demarcation for the project across 10 tehsils, using teams of tehsildars, girdawars and patwaris. The next step was to begin the Section 3D process. However, the matter remains pending at the NHAI level.

Meghraj Meena, Land Acquisition Officer and Additional District Magistrate-II, told Dainik Bhaskar that a third reminder was sent to NHAI on 16 November seeking action on the Section 3D notification. The Section 3A notification was issued in December 2025. According to the administration’s communication, the final notification must be published within the prescribed period, or the earlier notification will lapse.

If the deadline is missed, the administration may have to repeat land measurement, alignment demarcation, boundary marking and other formalities. That would delay the project further and add to the cost of work already undertaken. Dainik Bhaskar reported that around Rs 10 crore has so far been spent on land-related work, the detailed project report and other processes.

The land acquisition issue is also linked to an unresolved financial and policy framework between the state government and NHAI. A meeting chaired by Rajasthan’s chief secretary on 2 November discussed construction of the ring road under the Union Ministry of Road Transport and Highways’ Urban De-congestion Policy. However, the meeting did not settle the state’s financial contribution, the ratio for sharing land acquisition costs, reimbursement of goods and services tax and royalty, or the terms of a proposed memorandum of understanding between the state government and NHAI.

These unresolved issues have reportedly held back the Section 3D action. The project’s history shows that the delay is not limited to the current notification. The North Ring Road was included in Jaipur’s Master Plan-2025. In 2017, NHAI prepared a revised alignment for the North Corridor. The proposed route was extended from about 76 kilometres to roughly 96 kilometres to avoid an environmentally sensitive area.

The Section 3A process was taken forward in 2023 on the basis of a revised detailed project report, but the Section 3D notification was put on hold because of higher compensation costs. The alignment was subsequently moved about 20 kilometres away from the South Ring Road. Even after that change, questions over the state’s contribution, land acquisition costs, tax and royalty reimbursement, and the inter-governmental agreement remained unresolved.

The continuing delay could also increase the project’s eventual land acquisition burden. Dainik Bhaskar reported that district land valuation, or DLC, rates have risen three times during the period, with the cumulative increase said to be more than 25 per cent. Higher valuation rates can raise compensation requirements when acquisition proceeds.

Under Section 3A, land required for a public highway project is identified and notified after preliminary measurement and alignment work. Section 3D follows the disposal of objections and other required steps; its publication vests the notified land in the central government and allows the subsequent compensation process to move forward. For Jaipur, the immediate administrative question is whether that transition will be completed before the current notification expires.