Gurugram C&D Waste Pressure Grows With RERA Expansion
Gurugram is emerging as Haryana’s biggest construction and demolition waste hotspot, generating about 1,500 tonnes a day in 2024-25, or nearly 70% of the state’s daily total. The gap between waste generated and waste collected highlights a growing urban infrastructure risk as real estate and construction activity continue to expand faster than civic systems for handling debris.
Haryana generated around 2,150 tonnes of C&D waste each day during the period, according to the latest review by the Haryana State Pollution Control Board (HSPCB). Gurugram alone produced nearly five times the volume reported by Faridabad, the state’s second-largest generator at about 300 tonnes per day. Yet collection in Gurugram reached only around 300 tonnes daily. At the state level, roughly 680 tonnes was collected against the much larger generation volume, while reported processing capacity stood at 546.7 tonnes. The mismatch creates a clear risk of debris entering roadsides, vacant land, drains and low-lying areas. The problem is closely linked to the scale of urban construction. RERA-registered projects provide one indicator of formal real estate activity, although RERA itself is not the regulator responsible for C&D waste management. As Gurugram adds housing, commercial space and infrastructure, waste management needs to expand alongside the construction pipeline rather than after projects are completed.
The HSPCB review also points to weak disposal infrastructure across Haryana. Eleven districts relied on landfilling at 96 identified low-lying locations, with Palwal accounting for 77 such sites. More than 6,148 tonnes of C&D waste was reported as landfilled during 2024-25. Only Gurugram, Rewari, Ambala and Kaithal reported disposal through dedicated recycling or processing facilities. For Gurugram, the immediate challenge is expanding the network beyond its four operational storage sites. The city has identified 20 sites in total, with the remaining 16 planned by the end of 2026. Better storage and collection could reduce illegal dumping, but the larger issue is ensuring that collected material actually reaches processing facilities. The enforcement numbers also show the scale of the compliance challenge. Haryana’s urban local bodies issued 1,251 challans and imposed penalties of about ₹11.06 crore for violations during 2024-25.
However, monitoring remains heavily dependent on manual inspections, while segregation systems for different waste streams remain limited. Urban planners say the next phase of Gurugram’s growth will require construction waste to be treated as core infrastructure, alongside roads, drainage and mobility. For a city expanding through large-scale real estate and infrastructure projects, closing the collection and recycling gap will be essential to keeping growth cleaner, more resilient and less burdensome for residents.