Mumbai’s 440 million litres per day (MLD) Gargai Dam project has received wildlife clearance from the Standing Committee of the National Board for Wildlife (NBWL), bringing the proposed water-supply project closer to construction, according to a report by the Free Press Journal.

The Brihanmumbai Municipal Corporation (BMC) is now awaiting further forest, land and rehabilitation-related approvals. A senior civic official told the publication that the civic body expects the remaining approvals within two months and is targeting the start of construction in early 2027. The official meeting minutes confirming the wildlife clearance were still awaited, the report said.

The project is planned in Wada taluka of Palghar district, near Ogada village. It involves a 69-metre-high dam and a 2.2-km tunnel that would divert water into the Modak Sagar reservoir. The BMC aims to complete the dam and associated structures by May or June 2029 and begin storing and supplying water to Mumbai during the 2029 monsoon.

The project cannot move to full-scale construction until additional permissions and land-related processes are completed. These include two forest clearances—one from the Maharashtra government and another from the Centre—as well as compensatory afforestation and approvals for the rehabilitation and resettlement of affected villages.

The BMC has reportedly begun mobilising machinery and manpower at the site while preparing for the construction schedule. It plans to complete the main dam structure in nine months, compared with the 15 months taken to construct the Middle Vaitarna dam. The Central Design Organisation in Nashik, Maharashtra’s apex technical body for dam construction, has cleared the project’s basic design and structural aspects.

The dam is expected to use roller-compacted concrete, a construction material used in large dam projects. Rehabilitation work is also being pursued alongside the approval process, with the relocation of affected villagers expected to begin after the necessary permissions are secured.

The proposed reservoir and related works would have a significant environmental footprint. The project is expected to require the felling of around 3.1 lakh trees, including trees in areas within the Tansa Wildlife Sanctuary. Compensatory afforestation on non-forest land will therefore be required.

The BMC currently supplies about 4,100 MLD of water from seven lakes: Tansa, Bhatsa, Modak Sagar, Tulsi, Vihar, Upper Vaitarna and Middle Vaitarna. The Free Press Journal report said demand is estimated at 4,463 MLD and is projected to rise to 6,900 MLD by 2041. It also reported that about 34% of supplied water is lost through leakages and theft.

If the remaining clearances, land processes and rehabilitation measures are completed within the BMC’s projected schedule, Gargai would become the next major addition to Mumbai’s water infrastructure after the Middle Vaitarna dam, which was completed in 2014. Its stated 440 MLD capacity would add to the city’s supply system, while the project’s environmental and resettlement obligations remain important conditions for implementation.