Gaggal Airport Expansion Clears Court Hurdle, but Approvals Remain

The Himachal Pradesh High Court has upheld the proposed expansion of Kangra airport at Gaggal, allowing the state to proceed with land acquisition while warning that construction cannot begin without the required environmental approvals.

The Rs 4,064-crore project was challenged by the Gaggal Airport Expansion Affected Social Welfare Committee, which questioned the July 7, 2023, land acquisition notification and the associated social impact assessment. A division bench comprising Justice Vivek Singh Thakur and Justice Ranjan Sharma dismissed the petition after examining both the committee’s objections and the merits of the case, according to a report by The Times of India.

The court held that the expansion served a larger public interest and that the right to residence and livelihood under Article 21 of the Constitution could not override land acquisition for a project considered necessary in the public interest. The bench also noted that the committee did not have the legal standing to maintain the petition, but examined the substantive issues before finding no grounds to intervene.

The project is expected to require approximately 147.75 hectares of land. This includes 122.66 hectares of private land and 6.10 hectares of forest land, with the remaining area understood from the project details to comprise other land categories. More than Rs 460 crore has already reportedly been disbursed under land acquisition awards.

The ruling does not, however, amount to an unconditional clearance for construction. The court cautioned the state government against risking public funds without securing mandatory approvals. It directed the state to complete the techno-economic feasibility report at the earliest and begin steps for environmental clearance under the Environment Impact Assessment Notification, 2006, without waiting for the acquisition process to conclude. Project work, the court emphasised, can begin only after the necessary environmental clearances are obtained.

The court rejected objections relating to the seismic vulnerability of the Kangra region. It observed that the airport was already operational and referred to Bhuj airport in Gujarat as an example of an airport functioning in a high-risk seismic zone. The bench also declined to require an alternative site, noting that the proposal involved expansion of an existing airport rather than construction of a new facility.

The Airports Authority of India had told the court that alternative alignments were technically unsuitable and would require expensive bridges over river channels. A multidisciplinary expert group had concluded that no viable option involving less displacement was available, the report said.

The court also rejected allegations of irregularities in the social impact assessment process. It found no material establishing that alleged visits by the assessment team before the formal notification had violated the law or caused prejudice. The assessment was subsequently completed through a survey and public hearings conducted after public notices.

Kangra is one of three operational airports in Himachal Pradesh, alongside Bhuntar and Shimla. Gaggal airport, which began operations in 1989, has the state’s longest runway at 1,372 metres by 30 metres. The runway can accommodate 72-seater aircraft with a load penalty, while an ATR-42 currently operates from the airport with a load penalty.

The airport expansion is therefore moving past a significant legal hurdle, but its next phase remains dependent on feasibility documentation and environmental scrutiny. The court’s directions also place responsibility on the state and implementing agencies to establish that the proposed expenditure, land requirements and environmental impacts have been assessed before physical work begins.