Nearly 22,000 applications for land conversion are awaiting action across Ernakulam district’s taluks, excluding Kochi taluk, according to information disclosed in response to a Right to Information (RTI) application. The backlog has accumulated even as the government has collected more than Rs 295 crore in land-conversion fees from six taluks, highlighting the administrative strain behind one of the state’s key land-use procedures.
The figures were reported by Madhyamam based on a reply issued by the district collectorate and taluk offices to an RTI application filed by information-rights activist Raju Vazhakkala. The report said applications were pending in multiple taluks, with the number in individual offices ranging from about 1,500 to nearly 7,000.
Paravur taluk recorded the highest number of pending Form 6 applications, at 6,779. Kanayannur taluk, which includes the area centred on Ernakulam city, had 5,059 applications awaiting disposal. Kunnathunad had 2,760 pending applications, while Kothamangalam recorded the lowest figure among the taluks listed, at 1,415. The report did not provide the corresponding number for Kochi taluk; including it would increase the district-wide total.
The backlog matters because land conversion approval determines whether parcels recorded under one land-use classification can be used for another permitted purpose. For applicants, delays can hold up property transactions, construction-related decisions and other land-use steps. Madhyamam reported that hundreds of people, including ordinary applicants, were facing difficulties because their applications had not been settled within a reasonable period.
The disclosed figures also show the financial scale of the process. Kanayannur taluk collected Rs 122 crore in land-conversion fees, the highest among the taluks cited. Kunnathunad collected Rs 39 crore, Aluva Rs 36 crore and Paravur Rs 31 crore. Muvattupuzha and Kothamangalam together collected Rs 65 crore. The report said hundreds of hectares had already been converted across the district.
Under an amendment dated 30 December 2017, land up to 25 cents held as a single parcel by an applicant can be converted without a fee, according to the report. However, officials said the RELIS online portal does not have a facility to separately extract accurate figures for applications involving less than five cents under Form 6. That limitation makes it harder to produce a complete digital picture of the volume and characteristics of applications moving through the system.
Officials also explained that there is no legally fixed deadline for disposing of the applications. Each case requires scrutiny of documents and, in some instances, a site inspection. As a result, the time taken can vary from one application to another, they said.
The combination of a large pending caseload, substantial fee collection and the absence of a specific statutory disposal period leaves applicants with limited certainty about when a decision will arrive. It also makes it difficult to distinguish between cases delayed by incomplete documentation, those requiring field verification and those awaiting administrative action.
The RTI data therefore points to more than an isolated office-level delay. It shows a land-use administration system handling a high volume of applications across rapidly developing parts of Ernakulam, while operating with uneven data visibility and no uniform legal time limit for completion. The reported figures do not indicate how old the pending applications are, how many have incomplete records or what disposal rate each taluk has achieved. Those details would be necessary to assess whether the backlog is reducing and where additional administrative capacity is most urgently needed.