Chennai Metro Rail Limited (CMRL) has erected the last of 606 U-shaped concrete girders on the elevated stretch between Koyambedu Market and Alandur, completing the viaduct structure on a 14.5-km section of Phase II’s Corridor 5.
The final girder was lifted into position on Sunday between Butt Road and Kathipara on Paul Wells Road using two 550-tonne hydraulic cranes, CMRL said in a statement on Monday. The girders range from 15 metres to 33.33 metres in length and weigh about 135 tonnes each on average.
CMRL used launching girders at some locations and high-capacity cranes at others. Construction along Kaliamman Koil Street, Butt Road and Paul Wells Road was complicated by traffic congestion, underground and overhead utilities and limited working space, according to the statement.
The integrated flyover along Mount Poonamallee Road added to the construction challenge. At span P380-P381 on Paul Wells Road, the presence of a school and residential buildings left insufficient space to position cranes, CMRL said.
The construction team temporarily used part of the school campus during the Vijayadashami holidays. Sections of the compound wall and connecting passages were demolished for the operation, with CMRL stating that the structures would be restored before the school reopened.
The two 550-tonne cranes could not achieve the required lifting radius at the location, prompting the team to bring in a 1,000-tonne crane for the final operation, according to CMRL.