Western Railway will close Platform 5 at Mumbai’s Bandra Terminus for 75 days from December 1 to February 13, 2027, for track foundation repairs, according to a report citing railway officials. The work will alter the operation of several long-distance trains and affect suburban services on the western line.
The repair will involve removing the existing tracks and cement concrete apron before rebuilding the foundation in phases. A Western Railway official told the Hindustan Times, as quoted in the report, that the cement base supporting the tracks had sagged at several locations and could pose a safety risk. Long-distance trains entering the platform have reportedly been required to reduce speed, contributing to delays of about 20 to 30 minutes during peak periods.
During the block, some long-distance services will be diverted, some will be short-terminated at Borivali and others will use Dadar or Bandra Terminus as their operating terminal. The changes will also have a knock-on effect on local train operations because of the altered movement of long-distance services through the corridor.
Four suburban services will remain cancelled throughout the repair period. They are the Churchgate–Borivali fast local BO90559, scheduled at 2:50 pm; Borivali–Churchgate slow local BO90596, scheduled at 3:40 pm; Churchgate–Borivali fast local BO94105, scheduled at 5:28 pm; and Borivali–Churchgate fast local BO94110, scheduled at 6:24 pm.
Western Railway has also indicated that other local services could be delayed by up to 10 minutes during the block. The report says additional cancellations may be required depending on the diversion and short-termination arrangements for long-distance trains.
Four pairs of long-distance trains will have their terminals changed. The Bhuj–Bandra Terminus–Bhuj service, numbered 22956/22955, will operate from Dadar instead of Bandra Terminus. The Ajmer–Dadar–Ajmer service 12990/12989, Sri Ganganagar–Dadar–Sri Ganganagar service 12489/12490 and Bhagat Ki Kothi–Dadar–Bhagat Ki Kothi service 20483/20484 will operate from Bandra Terminus instead of Dadar.
Five incoming trains will be short-terminated at Borivali and will not continue to Bandra Terminus. These are the Bhuj–Bandra Terminus service 22904, which runs on Mondays, Thursdays and Saturdays; the daily Udhna–Bandra Terminus service 19056; the Madgaon–Bandra Terminus service 10116, operating on Tuesdays and Thursdays; the Jaipur–Bandra Terminus service 19723, operating on Wednesdays; and the Darbhanga–Bandra Terminus service 19625, operating on Sundays.
Four outgoing services will originate from Borivali rather than Bandra Terminus. They are the daily Bandra Terminus–Udhna service 19055; the Bandra Terminus–Madgaon service 10115, operating on Wednesdays and Fridays; the Bandra Terminus–Jaipur service 19724, operating on Thursdays; and the Bandra Terminus–Darbhanga service 19626, scheduled on Mondays.
The planned closure highlights the operational consequences of repairing a platform foundation while maintaining rail services at a busy terminal. Passengers using the affected long-distance trains will need to check whether their journey begins or ends at Bandra Terminus, Borivali or Dadar during the block. Suburban commuters may also need to allow additional travel time because of the announced cancellations and possible delays.
The reported repair sequence begins with Platform 5, while work on other platforms is expected to follow. The report does not provide a separate Western Railway circular detailing the full timetable, passenger-assistance arrangements or the precise phasing of subsequent platform work. Travellers should therefore verify service-specific changes with railway sources before starting their journey.