Jaipur road widening work from the Nandpuri underpass to Airport Road is progressing even as electricity poles and transformers remain within the planned carriageway, according to a report by Dainik Bhaskar. The 1.5-kilometre stretch is being widened from 40 feet to 80 feet.
The road has 67 electricity poles and four transformers. Asphalt has already been laid around poles between Airport Road and Nandpuri Mor, while work is continuing in Kailashpuri without the power lines being shifted, the report said. Poles positioned in the middle of the road are confusing motorists, it added.
The Jaipur Development Authority (JDA) had removed 260 houses and shops falling within the road boundary about six months ago to implement the widening under the zonal plan. The report said the structures were cleared in May.
The JDA’s electrical branch said work to shift the lines had begun. Naresh Shekhar, executive engineer in the branch, said the lines would be shifted in stages within two to three days after the required connections were made. He said the shifting would be completed before the road construction was finished to prevent accidents.
The sequencing of utility relocation and road construction remains the immediate issue on the project. Until the poles and transformers are moved, sections of the widened road will continue to operate around fixed electrical infrastructure, according to the report.