The Bahadur Sheikh Naka flyover in Chiplun, Ratnagiri district, is planned to open to general traffic on November 30, potentially easing congestion on the Mumbai-Goa National Highway through the town. The 1.48-kilometre structure is being opened after trial runs were conducted on both lanes on Thursday and Friday, according to Navbharat Times.
The National Highways Authority of India (NHAI) and the contractor have completed the flyover and both approach roads, the report said. Minor finishing work was expected to continue for another seven to eight days, while engineers monitored the trial traffic.
The flyover is supported by 95 pillars and has 182 slabs. A speed limit of 80 to 100 kilometres per hour has been set for vehicles using the structure, according to the report. Twenty-four-hour trial runs were planned to identify any technical or safety-related shortcomings before full opening. Contractor officials said the safety of the structure and motorists was the priority.
The project had remained delayed for several years. The report also said the earlier Bahadur Sheikh Naka flyover collapsed two years ago, without causing fatalities. It did not provide details of the collapse or identify the findings of any subsequent investigation.
Local residents have sought an extension of the flyover alignment towards Kapsala, including the Power House area, where they say accidents have occurred. A proposal has reportedly been prepared, but sources cited by the report said work on any extension would depend on traffic operating smoothly on the current flyover first.
Separately, construction of the Mangaon bypass in neighbouring Raigad district is progressing on the same highway. It is expected to open officially by the end of January, the report said. The November 30 date for the Chiplun flyover is an NHAI plan and had not yet been confirmed as an operational opening at the time of publication.