The redevelopment of Sewri’s BDD chawls could move forward after a meeting between the Maharashtra Housing and Area Development Authority (MHADA) and the Mumbai Port Authority on land transfer, technical obstacles and the required no-objection clearances, according to a report by Loksatta.
The 12 buildings, located on Mumbai Port Authority land, house 960 families. Loksatta reported that the structures have deteriorated significantly and that redevelopment has been delayed for several years because the land must be transferred to the state government and clearances from the Centre are required.
A joint meeting involving MHADA vice-president Sanjeev Jaiswal, Mumbai Port Authority chairman Dr M. Angamuthu, officials and residents’ organisations was held on Wednesday. Member of Parliament Milind Deora also attended, the report said. A senior MHADA official told Loksatta that the discussion was positive.
MHADA is expected to submit a proposal seeking the required no-objection certificate. The Mumbai Port Authority is also expected to pursue the land transfer and the clearance process with the central government, according to the report.
The port authority has indicated that it is willing to transfer the land to the state government after outstanding dues and the value of the plot are paid. Loksatta reported that the combined amount could be approximately Rs 450 crore, which MHADA would have to pay to take possession of the land.
The land-transfer requirement is central to the redevelopment process. Unlike the BDD chawls at Worli, Na M Joshi Marg and Naigaon, whose redevelopment is being undertaken through MHADA’s Mumbai Board, the Sewri project has remained pending because the site is controlled by the Mumbai Port Authority.
The latest meeting does not, however, amount to a redevelopment approval or a construction start date. The proposal, central clearance, land transfer and financial payment would still have to be completed before the project can proceed to implementation. The report did not provide a confirmed timeline for these steps.
For residents, the immediate significance lies in whether the discussions lead to formal documentation and a defined institutional process. Until the land is transferred and the necessary clearances are secured, the redevelopment of the Sewri BDD chawls will remain at the preparatory stage.