Airoli-Katai Naka elevated road may ease Dombivli commute

The Airoli-Katai Naka elevated road project linking Navi Mumbai with Dombivli and Kalyan could open two sections to traffic by the end of December, according to a report by Loksatta. The proposed opening covers sections that are nearing completion, but the report describes the timeline as a possibility rather than a confirmed date.

The first section runs for 3.43 kilometres between Thane-Belapur Road and National Highway-4. It includes a 1.69-kilometre twin tunnel and a 0.94-kilometre elevated road. The second section connects Airoli with Thane-Belapur Road. Once these two sections are opened, work on the project’s final, or third, phase is expected to gain momentum, the report said.

The project has a planned total length of 12.71 kilometres and is being developed in three phases. The first phase includes two tunnels, each designed with three traffic lanes and one emergency lane. Ventilation, firefighting equipment, a high-pressure water-mist system, lighting and driver information signs are being installed in the tunnels. According to the report, work on these systems is in its final stage.

The road is intended to improve travel between Navi Mumbai and the growing residential areas of Dombivli and Kalyan. Loksatta reported that thousands of employees travel daily between these locations for work, while congestion around Shilphata creates delays during the morning, evening and night periods. In some cases, commuters are reportedly held up in traffic for hours, making it difficult to reach workplaces on time.

The transport pressure is also being intensified by expanding housing development in Dombivli and the Shilphata area. The report said that rising population and vehicle numbers have increased the load on existing roads, making the Airoli-Katai Naka link a significant regional connectivity project.

If the two sections open as reported, commuters could receive an alternative connection before the entire 12.71-kilometre project is completed. However, the report does not provide a confirmed inauguration date, details of the implementing agency or a revised schedule for the final phase. The extent to which the initial openings will reduce congestion will therefore depend on how the sections connect with the existing road network and when the remaining work is completed.