Construction of a retaining wall has accelerated near the Martyrs’ Memorial inside Secunderabad’s Parade Grounds as work advances on the Paradise Circle-Outer Ring Road Shamirpet elevated corridor, according to Telangana Today’s report citing Hyderabad Metropolitan Development Authority (HMDA) officials and sources.
The retaining wall is being built along Gymkhana Grounds as part of road-widening works for the proposed elevated corridor on State Highway-1, also known as Rajiv Rahdari. The project is intended to address traffic bottlenecks along the Secunderabad-Paradise-Gymkhana-Shamirpet stretch.
HMDA is relocating two memorials at the Parade Grounds after receiving approval from the Secunderabad Cantonment Board, the report said. They are the World War II memorial and the Veerula Sainik Smarak. Work on a new platform for the memorials is under way and is expected to be completed by December, according to HMDA sources cited in the report.
The new Martyrs’ Memorial is estimated to cost Rs 5 crore and is scheduled to be installed by March or April 2027, officials said. The relocation is taking place as land is acquired for the elevated corridor. The report said land extending up to 20 metres from the road alongside the existing memorial platform inside Parade Grounds is being acquired.
HMDA sources also said landscaped lawns and several decades-old trees near the Martyrs’ Memorial had recently been cleared to make way for the retaining wall. The work is therefore changing the appearance and use of a prominent public space even as civil construction moves into structural execution.
The elevated corridor will be 18.18 km long and have six lanes. It will run from Paradise Junction in Secunderabad to the Outer Ring Road junction at Shamirpet. According to the report, the alignment is designed to bypass traffic bottlenecks at Karkhana, Trimulghery, Lothkunta, Bolarum, Alwal, Machabollaram, Hakimpet and Thumkunta.
The project is estimated to cost Rs 2,232 crore and is targeted for completion within 24 months. HMDA officials described the corridor as part of the Telangana government’s effort to ease congestion on key northern arteries.
The current work marks a shift from preliminary groundwork to structural execution around Parade Grounds. For residents and road users, the construction will affect a major route through Secunderabad Cantonment and the northern approaches to Hyderabad. The relocation of the memorials and the reported clearance of lawns and trees also make the treatment of public spaces an immediate concern alongside the corridor’s transport objectives.
The report did not provide details on the final design of the relocated memorials, the number of trees cleared or the traffic-management arrangements during construction.