Hyderabad Sets January 2027 Target for Musi Phase-I Works

Hyderabad’s Musi rejuvenation project is targeted to begin Phase-I works in January 2027, with the 21-km package divided between two zones along the river, according to officials who briefed Chief Minister A. Revanth Reddy at a review meeting on municipal administration and urban development.

Officials said Zone-1A would cover 9.2 km from Himayatsagar to Gandhi Sarovar, while Zone-1B would cover 11.8 km from Osmansagar to Gandhi Sarovar. The tendering process for the Phase-I works had begun, the report said. Revanth Reddy directed officials to expedite preparations for the project.

The meeting also examined a proposed Phase-I Personal Rapid Transit System (PRTS) for Hyderabad. Officials presented a techno-economic feasibility study and outlined a possible alignment from Kukatpally through Raidurg to Biodiversity. A second proposed alignment would run from Begumpet Metro station through the Secretariat and Basheerbagh to Ranigunj.

The chief minister asked officials to identify suitable locations for PRTS depots at PVNR Marg, Raidurg and People’s Plaza. He also directed them to examine multi-level parking facilities around the proposed depots and complete a comprehensive study covering routes, depot construction and related requirements before final plans are prepared.

The proposed PRTS remains at the study and planning stage in the account of the meeting. The report does not provide a construction schedule, estimated cost or final alignment. Its immediate significance is that the state government is linking route planning with depot locations and parking requirements before preparing the final project plans.

Other instructions at the review meeting covered several connected urban works. Revanth Reddy reviewed development at Miralam Tank, where officials said completion was targeted for January 2028, and directed them to remove long-pending silt while carrying out the tank’s development works.

He also directed officials to accelerate radial road construction and land acquisition. A modern goshala under construction at Gandipet was targeted for completion by March 2027. At IIIT Junction, he reviewed designs for a footbridge and asked officials to explore a multi-level car park near the facility.

The integrated fruit market at Koheda was another item on the agenda. The chief minister directed officials to speed up the work without compromising quality and to complete the road works alongside the market development to improve connectivity and transportation facilities.

Lake restoration and protection of government properties in the CURE region were also reviewed. HYDRAA commissioner A.V. Ranganath briefed the meeting on proposals to establish sewage treatment plants wherever necessary as part of lake restoration. The chief minister directed officials to expedite STP construction and take measures to restore step wells in Hyderabad.

The range of directions shows that the Musi project is being reviewed alongside drainage, lake protection, roads, parking, public transport and land-related works. The meeting also brought several agencies and officials into the same review process, including HMDA, HYDRAA, GHMC, HMWS&SB, MRDCL and other municipal and regional bodies.

The next measurable steps identified in the report are the continuation of tendering and preparations for the January 2027 start of Musi Phase-I works; further feasibility work for the PRTS routes and depots; and acceleration of the lake, road, market, parking and sewage-treatment projects. The report does not state whether the proposed PRTS alignments or depot locations have received final approval.