Bullet Train OHE Energisation Advances Surat–Bilimora Testing

The Mumbai–Ahmedabad High-Speed Rail project has energised the overhead equipment (OHE) system on the Surat–Bilimora section in Gujarat, advancing preparations for the next phase of testing on India’s first bullet train corridor.

According to a report by NBM&CW, energisation was completed on November 20, 2026, across both Up and Down lines along the elevated alignment. The process is being undertaken progressively in smaller sections under the supervision of technical teams, with safety and prescribed procedures guiding the work.

The Surat–Bilimora stretch covers approximately 50 km and includes bridges over four rivers as well as a steel bridge over National Highway 53. The viaduct has also been fitted with approximately 94,000 noise barriers, according to the report.

The 508-km Mumbai–Ahmedabad corridor uses a 2 × 25 kV overhead traction system, a configuration used in high-speed rail networks. Fourteen traction substations are planned along the corridor to draw electricity from the national grid and supply the overhead traction network.

The first traction substation at Bilimora in Gujarat’s Navsari district has completed installation of equipment in its control panel, changeover switch, transformer and circuit breaker buildings. It will receive power from the 220 kV Ambetha Grid Substation operated by Gujarat Energy Transmission Corporation Limited, or GETCO.

A centralised control centre is intended to monitor the electrical network and support safe and reliable operations. The energisation of the OHE system is therefore an infrastructure and systems-integration milestone rather than the start of passenger service. Further testing and commissioning will be required before operations can begin, although the report does not provide a passenger-service date for this section.

The new electrical status also changes the immediate safety conditions around the alignment. Residents, commuters, construction workers and other members of the public near the Surat–Bilimora section have been advised not to approach or touch overhead electrical installations or carry out unauthorised work near them.

For communities along the elevated corridor, the advisory is particularly relevant as construction and related access activity continues around viaducts, bridges and utility installations. The staged energisation approach allows technical teams to bring sections into service progressively while maintaining safety controls around the traction infrastructure.